REGULAR MEETING ARPIL 14, 2026 79
<br />
<br />
<br />APPROVE CHANGE ORDER NO. 3 – ND TO DTSB TRAIL – PROJECT NO. 122-040A (PO-
<br />0030356)
<br />President Maradik advised that Charlotte Brach, Engineering, has submitted change order
<br />number 3 on behalf of Milestone Contractors, L.P., indicating the contract amount be
<br />increased by $49,926.51 for a new contract sum, including this change order, in the amount
<br />of $5,673,109.40 and additional one (1) day. Upon a motion made by VP Molnar, seconded
<br />by Mr. Miller and carried by roll call, the change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 6 – RACLIN MURPHY ENCORE CENTER – PROJECT
<br />NO. 123-056 (PO-0032487)
<br />President Maradik advised that Patrick Sherman, Engineering, has submitted change order
<br />number 6 on behalf of Larson-Danielson Construction Co., Inc. , indicating the contract
<br />amount be increased by $64,989.70 for a new contract sum, including this change order, in
<br />the amount of $16,099,214.79. Upon a motion made by VP Molnar, seconded by Mr. Miller
<br />and carried by roll call, the change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 1 – STUDEBAKER MUSEUM SKYLIGHT
<br />REPLACEMENT – PROJECT NO. 124-019 (PO-0035275)
<br />President Maradik advised that Patrick Sherman, Engineering, has submitted change order
<br />number 1 on behalf of Shaffner Heaney and Associates, indicating the contract amount be
<br />increased by $1,500 for a new contract sum, including this change order, in the amount of
<br />$78,447 with an additional two-hundred and fifteen (215) days and a completion date of
<br />November 1, 2025. Upon a motion made by VP Molnar, seconded by Mr. Miller and carried
<br />by roll call, the change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 1 – O’BRIEN SPLASHPAD AND RESTROOM – PROJECT
<br />NO. 125-025 (PO-0041970)
<br />President Maradik advised that Zak Tebell, Engineering, has submitted change order
<br />number 1 on behalf of C&E Excavating, Inc., indicating the contract amount be increased by
<br />$5,445 for a new contract sum, including this change order, in the amount of $1,547,868.
<br />Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by roll call, the
<br />change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 5 – BEACON HEALTH PARKING LOT – PROJECT NO.
<br />123-076A (PO-0036234)
<br />President Maradik advised that Zach Hurst, Engineering, has submitted change order
<br />number 5 on behalf of Indiana Earth, Inc., indicating the contract amount be increased by
<br />$3,883.75 for a new contract sum, including this change order, in the amount of
<br />$2,682,951.72. Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by
<br />roll call, the change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 1 – DEMOLTION OF FORMER NIPSCO BUILIDNG –
<br />PROJECT NO. 125-080 (PO-0042066)
<br />President Maradik advised that Zach Hurst, Engineering, has submitted change order
<br />number 1 on behalf of Ritschard Bros., Inc., indicating the contract amount be increased by
<br />$7,500 for a new contract sum, including this change order, in the amount of $246,216.
<br />Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by roll call, the
<br />change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 1(F) – WWTP HEADWORKS OFFICE IMPROVEMENTS
<br />– PROJECT NO. 125-023 (PO-0041167)
<br />President Maradik advised that Gemma Stanton, Engineering, has submitted change order
<br />number 1 (F) on behalf of Larson-Danielson Construction Co., Inc., indicating the contract
<br />amount be increased by $2,046.12 for a new contract sum, including this change order, in
<br />the amount of $68,516.12 and an additional eighty-three (83) day with a completion date
<br />of January 1, 2026. Upon a motion made by VP Molnar, seconded by Mr. Miller and carried
<br />by roll call, the change order was approved.
<br />
<br />APPROVE CHANGE ORDER NO. 1 – SRTS KENNEDY SCHOOL – PROJECT NO. 123-017
<br />(PO-0041449)
|