Laserfiche WebLink
Madison Lifestyle District - CMc RFP Response • Shiel Sexton | 16Confidential material included on this page. <br />CITY/OWNER PROJECT SPECIFIC GOALS (continued) <br />5. PROJECT SCHEDULE: <br />It will be important for the proposer to be able to describe what a conceptual schedule looks like for the commencement <br />and completion of the project based on the anticipated dates in the schedule D6 of this document. <br />CMc CONTRACT <br />If the Owner does not have a proposed form of contract, Shiel Sexton proposes a modified AIA A133 and A201 and can <br />supply a copy upon award. Shiel Sexton will then work closely with the Owner and/or its counsel to finalize. This can be <br />completed within a week or two. The GMP Amendment (Exhibit A, A133) will then be completed after bidding the first <br />tier trade packages. <br /> Run Date: 12/13/2024 <br /> Progress Date: 8/3/2025 <br />Page 1 of 1 <br />Madison Lifestyle District - Phase 1 Parking Garage <br />City of South Bend <br />Proposal Schedule <br />Line Act. ID Activity Name Dur. Start Finish <br />20262025 2027 <br />September October November December January February March April May June July August September October November December January FebruaryAugust March <br />1 <br />2 <br />3 <br />4 <br />5 <br />6 <br />7 <br />8 <br />9 <br />10 <br />11 <br />12 <br />13 <br />14 <br />15 <br />16 <br />17 <br />18 <br />19 <br />20 <br />21 <br />22 <br />23 <br />24 <br />25 <br />26 <br />27 <br />Precast Parking Garage <br />1180 <br />1190 <br />1410 <br />1200 <br />1290 <br />1210 <br />1390 <br />1240 <br />1220 <br />1230 <br />1270 <br />1250 <br />1260 <br />Cast in Place Parking Garage <br />0030 <br />1280 <br />1310 <br />1320 <br />1420 <br />1380 <br />1400 <br />1370 <br />1330 <br />1360 <br />1350 <br />1340 <br />Site Prep & Stabilization <br />Foundations & Elevator Pit <br />Potential Weather Delays <br />Precast <br />Podium Wrap <br />Topping Slabs <br />Exterior Facade <br />MEP/FP Rough Ins <br />Underslab MEP <br />Slab on Grade <br />Install Stairs <br />MEP/FP Finishes <br />Install Elevators <br />Site Prep & Stabilization <br />Foundations & Elevator Pit <br />Underslab MEP <br />Slab on Grade <br />Potential Weather Delays <br />Cast in Place Structure <br />Exterior Facade <br />Podium Wrap <br />MEP/FP Rough Ins <br />Install Stairs <br />Install Elevators <br />MEP/FP Finishes <br />20d <br />30d <br />20d <br />100d <br />60d <br />50d <br />90d <br />75d <br />10d <br />15d <br />45d <br />30d <br />60d <br />20d <br />30d <br />10d <br />15d <br />25d <br />180d <br />90d <br />60d <br />75d <br />45d <br />60d <br />30d <br />04Aug25 <br />02Sep25 <br />14Oct25 <br />11Nov25 <br />09Feb26 <br />06Apr26 <br />06Apr26 <br />18May26 <br />02Jun26 <br />16Jun26 <br />08Jul26 <br />12Aug26 <br />12Aug26 <br />04Aug25 <br />02Sep25 <br />14Oct25 <br />28Oct25 <br />18Nov25 <br />26Dec25 <br />30Jun26 <br />15Jul26 <br />05Aug26 <br />10Sep26 <br />05Nov26 <br />05Nov26 <br />29Aug25 <br />13Oct25 <br />10Nov25 <br />03Apr26 <br />01May26 <br />15Jun26 <br />11Aug26 <br />01Sep26 <br />15Jun26 <br />07Jul26 <br />09Sep26 <br />23Sep26 <br />04Nov26 <br />29Aug25 <br />13Oct25 <br />27Oct25 <br />17Nov25 <br />23Dec25 <br />09Sep26 <br />04Nov26 <br />07Oct26 <br />18Nov26 <br />11Nov26 <br />02Feb27 <br />17Dec26 <br />Site Prep & Stabilization <br />Foundations & Elevator Pit <br />Potential Weather Delays <br />Precast <br />Podium Wrap <br />Topping Slabs <br />Exterior Facade <br />MEP/FP Rough Ins <br />Underslab MEP <br />Slab on Grade <br />Install Stairs <br />MEP/FP Finishes <br />Install Elevators <br />Site Prep & Stabilization <br />Foundations & Elevator Pit <br />Underslab MEP <br />Slab on Grade <br />Potential Weather Delays <br />Cast in Place Structure <br />Exterior Facade <br />Podium Wrap <br />MEP/FP Rough Ins <br />Install Stairs <br />Install Elevators <br />MEP/FP Finishes <br />Site Prep & Stabilization <br />Foundations & Elevator Pit <br />Potential Weather Delays <br />Precast <br />Podium Wrap <br />Topping Slabs <br />Exterior Facade <br />MEP/FP Rough Ins <br />Underslab MEP <br />Slab on Grade <br />Install Stairs <br />MEP/FP Finishes <br />Install Elevators <br />Site Prep & Stabilization <br />Foundations & Elevator Pit <br />Underslab MEP <br />Slab on Grade <br />Potential Weather Delays <br />Cast in Place Structure <br />Exterior Facade <br />Podium Wrap <br />MEP/FP Rough Ins <br />Install Stairs <br />Install Elevators <br />MEP/FP Finishes <br />PROJECT APPROACH