REGULAR MEETING
<br />JULY 8, 2025 143
<br />C
<br />Bid Total No Bid Amount
<br />Submitted
<br />Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by roll call, the above
<br />bids were referred to Central Services for review and recommendation.
<br />OPENING OF QUOTATIONS — URBAN HALF MOON NURSERY — PROJECT NO. 125-017R
<br />(PR-00040816)
<br />President Maradik advised that this was the date set for the receiving and opening of sealed
<br />quotations for the above referenced project. The following quotation was opened and read:
<br />ACORN LANDSCAPING LLC
<br />3680 West Sample Street
<br />South Bend, IN 46619
<br />j effritschardkyahoo. com
<br />Quotation was submitted by Ms. Andrea Ritschard
<br />Non -Collusion, Non -Discrimination Affidavit Form was completed.
<br />Three (3) Forms MWBE-1.0, 2.0, 2.1 were completed.
<br />QUOTATION:
<br />Base Quote Total
<br />$134,367
<br />Allowance 1
<br />$25,000
<br />Alternate 1
<br />$1,265
<br />Alternate 2
<br />$5,445
<br />Alternate 3
<br />$22,617
<br />Alternate 4
<br />$66,519
<br />Alternate 5
<br />$68,966
<br />Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by roll call, the above
<br />quotations were referred to Engineering and Venues Parks & Arts for review and
<br />recommendation.
<br />AWARD BID AND APPROVE CONTRACT — SOUTH WELL FIELD. WATER TREATMENT
<br />PLANT, AND DISTRIBUTION SYSTEM IMPROVEMENTS — BID PACKAGE 2, DIVISION
<br />A — PROJECT NO. 117-059A (SOUTHSIDE TIF AND WATER CAPITAL FUND)
<br />Jacob Klosinski, Engineering, advised the Board that on June 10, 2025, bids were received and
<br />opened for the above referenced project. After reviewing those bids, Mr. Klosinski recommended
<br />that the Board award the contract to the lowest responsive and responsible bidder, R. Yoder
<br />Construction, Inc., in the amount of $3,670,297. Therefore, VP Molnar made a motion that the
<br />recommendation be accepted, and the bid be awarded, and the contract approved as outlined above.
<br />Mr. Miller seconded the motion, which carried by roll call.
<br />AWARD BID AND APPROVE CONTRACT — SOUTH WELL FIELD. WATER TREATMENT
<br />PLANT, AND DISTRIBUTION SYSTEM IMPROVEMENTS — BID PACKAGE 2, DIVISION
<br />B — PROJECT NO. 117-059A (SOUTHSIDE TIF AND WATER CAPITAL FUND)
<br />Jacob Klosinski, Engineering, advised the Board that on April 22, 2025, bids were received and
<br />opened for the above referenced project. After reviewing those bids, Mr. Klosinski recommended
<br />that the Board award the contract to the lowest responsive and responsible bidder, C & E
<br />Excavating, Inc., in the amount of $936,674. Therefore, VP Molnar made a motion that the
<br />recommendation be accepted, and the bid be awarded, and the contract approved as outlined above.
<br />Mr. Miller seconded the motion, which carried by roll call.
<br />AWARD OUOTATION AND APPROVE CONTRACT — DEMOLITION OF 4022 OLD
<br />CLEVELAND ROAD — PROJECT NO. 125-038 (PR-00041653)
<br />Zach Hurst, Engineering, advised the Board that on June 24, 2025, quotations were received and
<br />opened for the above referenced project. After reviewing those quotations, Mr. Hurst
<br />recommended that the Board award the contract to the lowest responsive and responsible quoter,
<br />Ritschard Bros., Inc., in the amount of $29,251. Therefore, VP Molnar made a motion that the