2023.03157/2024.00254 <br />d) Meetings: none <br />e) Deliverables: compiled map of existing utilities (native GIS files and annotated pdf exhibit <br />showing horizontal alignment) <br />3) Demands <br />a) Estimate utility demands for facilities in project area, identified as existing, to-be- <br />demolished, or future. Demand calculations will consider the following. <br />i) Building system loads (minimum, average day, maximum day, and peak hour), <br />including fire protection (provided by others). <br />ii) Owner redundancy requirements (provided by others) <br />iii) Regulatory requirements by the Indiana Department of Environmental Management, <br />Indiana Administrative Code (327 IAC 3 and 8), and local authorities having <br />jurisdiction (AHJs). <br />iv) Recommended Standards for Water Works and Wastewater Facilities (aka 10 States’ <br />Standards) <br />b) Assumptions/exclusions: where data gaps exist, estimates will be based on documented <br />assumptions and recommendations will be made for additional data collection during <br />design phase <br />c) Meetings: one design team coordination meeting <br />d) Deliverables: matrix identifying facility, location, size, utility demand projections, timing of <br />needs, points of connection, preliminary utility sizing, governing design guidelines, and <br />source of information. <br />4) Sizing <br />a) Based on utility demand projections, determine ideal sizing of potable water, sanitary <br />sewer, and natural gas mains based on design best practices. Review sizing of existing <br />utilities and identify where assets may require more detailed analysis during design to <br />determine what if any upsizing will be needed. <br />b) Assumptions/exclusions: utility sizing will not be completed until demand projections are <br />finalized <br />c) Meetings: none <br />d) Deliverables: compiled utility plan annotated to identify areas where upsizing mains may <br />require more detailed analysis <br />5) Utility Plan - Proposed <br />a) Coordinate with the design team on building and site configurations, develop a concept <br />level layout to serve the new facilities including extensions and/or relocations of <br />underground utilities. <br />DocuSign Envelope ID: E68A204F-EF94-4F07-9C0D-73FE7469F8D3