Laserfiche WebLink
REGULAR MEETING <br />FEBRUARY 25, 2020 38 <br />QUALITY WINDOW TREATMENTS. INC. <br />50803 Stonebridge Dr. <br />Granger, IN 46530 <br />Non -Collusion, Non -Discrimination Affidavit Form was completed <br />Quotation was submitted by Terry Muston <br />QUOTATION: $3,128.06 <br />Upon a motion made by Ms. Maradik, seconded by Mr. Molnar and carried, the above quotation <br />was referred to Central Services for review and recommendation. <br />APPROVAL OF REQUEST TO REJECT BIDS — WASTEWATER TREATMENT PLANT <br />SECONDARY AND DISINFECTION IMPROVEMENTS— PROJECT NO. 119-069 <br />(UTILITIES, SEWAGE WORKS CAPITAL <br />In a memorandum to the Board, Mr. Jacob Klosinski, Engineering, requested permission to reject <br />all bids for the above referenced project due to exceeding the budget. Therefore, upon a motion <br />made by Ms. Maradik, seconded by Mr. Molnar and carried, the above request was approved. <br />APPROVE CHANGE ORDER NO. 2 — THREE TWENTY AT THE CASCADE — PROJECT <br />NO. 118-074A (REDA TIFF <br />Mr. Gilot advised that Mr. Zach Hurst, Engineering, has submitted Change Order No. 2 on <br />behalf of Precision Wall Systems, 3801 S. Main St., South Bend, IN 46614, indicating the <br />contract amount be increased by $32,034 and an additional one -hundred, fifty-two (152) days, <br />for a new contract sum including this Change Order, in the amount of $1,504,666 and a revised <br />completion date of March 15, 2020. Upon a motion made by Ms. Maradik, seconded by Mr. <br />Molnar and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 (FINAL) AND PROJECT COMPLETION AFFIDAVIT <br />— 2019 CONTRACTOR PAVING — PROJECT NO 119-062 (EDIT) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1, on behalf <br />of Rieth Riley Construction Co., Inc., 25200 State Road 23, South Bend, IN 46614, indicating <br />the contract amount be decreased by $18,812.23 for a new contract sum, including this Change <br />Order, of $442,456.77. Also submitted was the Project Completion Affidavit indicating this new <br />final cost of $442,456.77. Upon a motion made by Ms. Maradik, seconded by Mr. Molnar and <br />carried, Change Order No. 1 (Final) and the Project Completion Affidavit were approved. <br />APPROVE PROJECT COMPLETION AFFIDAVIT — FIRE STATION NO. 9 — PROJECT NO. <br />116-012 (2018 FIRE STATION NO. 9 CAPITAL) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted the Project Completion <br />Affidavit on behalf of Ziolkowski Construction, Inc., 4050 Ralph Jones Dr., South Bend, IN <br />46628, for the above referenced project, indicating a final cost of $3,681,702.50. Upon a motion <br />made by Ms. Maradik, seconded by Mr. Molnar and carried, the Project Completion Affidavit <br />was approved. <br />APPROVAL OF REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS SIX <br />THOUSAND (6,000), MORE OR LESS UNIVERSAL NESTABLE REFUSE CONTAINERS <br />— SPEC B (SOLID WASTE OPERATIONS) <br />In a memorandum to the Board, Mr. Matt Chlebowski, Central Services, requested permission to <br />advertise for the receipt of bids for the above referenced containers. Therefore, upon a motion <br />made by Ms. Maradik, seconded by Mr. Molnar and carried, the above request was approved. <br />APPROVAL OF REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS ONE (1) OR <br />MORE 2020 OR NEWER 6 YARD FRONT END RUBBER TIRE LOADER — SPEC A <br />(ORGANIC RESOURCES CAPITAL EQUIPMENT) <br />In a memorandum to the Board, Mr. Jeff Hudak, Central Services, requested permission to <br />advertise for the receipt of bids for the above referenced equipment. Therefore, upon a motion <br />made by Ms. Maradik, seconded by Ms. Molnar and carried, the above request was approved. <br />APPROVAL OF REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS 2020 LAWN <br />MAINTENANCE AND MENTORSHIP PROGRAM PACKAGE A AND PACKAGE B — <br />PROJECT NO. 1203-2020 (VPA MAINTENANCE) <br />In a memorandum to the Board, Mr. Patrick Sherman, Venus, Parks and Arts, requested <br />permission to advertise for the receipt of bids for the above referenced projects. Therefore, upon <br />