7. <br />BUSINESS (Cont'd <br />d. Force Account, Phase III -B: Authorization was requested to FORCE <br />establish a Force Account between the Department of Redevelop- ACCOUNT <br />ment and the South Bend Water Works, for Phase III -B, with a APPROVED, <br />total cost estimate of $10,850.00, Project Indiana R -66, per PHASE III -B, <br />letter dated September 19, 1975, from Mr. William P. Dillon, R -66 <br />Project Engineer, Water Works. <br />The water work to be done is summarized as service line and <br />fire hydrant relocations, new required service lines and <br />hydrants, replacement of aged service lines, and demolition of <br />unused service lines. <br />The expenditure is not to exceed the following, unless specific <br />change orders are issued by our department: . <br />Phase II -B Cost Estimate: <br />Replace 17 services with 1" copper line @ $550 = $ 9,350.00 <br />Replace 1 service with 2" copper line @ $750 = 750.00 <br />Replace 1 manhole with roadway box @ $150 = 150.00 <br />Demolish 8 unused service lines @ 75 = 600.00 <br />Total $10,850.00 <br />Motion was made by Mr. Wiggins, seconded by Mr. Chenney and <br />carried, to establish the above Force Account, between the <br />Department of Redevelopment and the South Bend Water Works, for <br />Phase III -B, with an amount not to exceed $10,850.00, Project <br />Indiana R -66. <br />GRESS REPORTS <br />a. Project E -7, Bureau of Housing Report: Mr. Kenneth J. Schaller, BUREAU OF <br />Project Director, submitted the following: As of September 30th, HOUSING <br />the statistics of the program reveal that sixty -six (66) homes REPORT, <br />are on contract. Thirty -five (35) Notices to Proceed have been E -7 <br />issued and twenty -one (21) homes have been completed. Progress <br />inspections are being conducted early during the construction <br />phases of each structure. <br />b.1 Southeast Project Report (Community Development): This written SOUTHEAST <br />report was also submitted by Mr. Kenneth J. Schaller, Project PROJECT <br />Director: In summarizing the monthly report, there have been REPORT <br />thirty -two (32) applicants to the Housing Rehabilitation Assis- (C.D.) <br />tance Program; nine (9) applicants have been approved and two <br />(2) rejected. <br />The nine approved applicants have been placed on contract set <br />one presently being advertised for bids. Bid opening date is <br />October 2. Other qualified applicants are being prepared for <br />inclusion into contract set two which will be ready to be ad- <br />vertised shortly. <br />Copy of the report, consisting of seven pages, have been re- <br />ceived and placed on file. <br />- 14 - <br />