~? ~ <br />REGULAR MEETING JANUARY 28, 2008 <br />APPROVE CHANGE ORDERS NO. 3 AND NO. 6 -SOUTH MICHIGAN STREET RE- <br />CONSTRUCTION - PROJECT NO. 104-024 (INDOT/FHWA) <br />Mr. Gilot advised that Ms. Thia Vawter, Engineering, has submitted Change Order Nos. 3 and 6 <br />on behalf of Walsh & Kelly, Inc., 24358 State Road 23, South Bend, Indiana 46614. Change <br />Order No. 3 indicates the Contract amount be increased by $4,881.50. Change Order No. 6 <br />indicates the Contract amount be increased by $6,862.00. The total of both change orders <br />increases the Contract for a new sum in the amount of $3,052,640.73. Upon a motion made by <br />Mr. Gilot, seconded by Mr. Littrell and carried, the Change Orders were approved. <br />APPROVE CHANGE ORDER NO. 1 AND PROJECT COMPLETION AFFIDAVIT - , <br />DEMOLITION OF CAROLINE PARTNERSHIP LLC PROPERTIES -PROJECT NO. 107- <br />079 (CIP/DEVELOPER~ <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 on behalf <br />of C&E Excavating, 53767 County Road 9, Elkhart, Indiana 46514, indicating the contract <br />amount be decreased by $10,000.00 for a new contract sum, including this Change Order, of <br />$148,112.00. Additionally submitted was the Project Completion Affidavit indicating this new <br />final cost of $148,112.00. Upon a motion made by Mr. Gilot, seconded by Mr. Inks and carried, <br />Change Order No. 1 and the Project Completion Affidavit were approved subject to the filing of <br />the appropriate three-year Maintenance Bond. <br />APPROVE CHANGE ORDER NO. (FINALI AND PROJECT COMPLETION AFFIDAVIT - <br />MIAMI STREETSCAPES - PROJECT NO. 107-013 (COIT) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering has submitted Change Order No. (Final) on <br />behalf of Walsh & Kelly, Inc., 24358 State Road 23, South Bend, Indiana 46614 indicating the <br />contract amount be decreased by $10,332.90 for a new contract sum, including this Change <br />Order, of $116,495.60. Additionally submitted was the Project Completion Affidavit indicating <br />this new final cost of $116,495.60. Upon a motion made by Mr. Inks, seconded by Mr. Littrell <br />and carried, Change Order No. (Final) and the Project Completion Affidavit were approved <br />subject to the filing of the appropriate three-year Maintenance Bond. <br />APPROVE CHANGE ORDER NO. (FINAL) AND PROJECT COMPLETION AFFIDAVIT - <br />YARD LAMPPOST PROGRAM 2007 - PROJECT NO. 107-034 (GENERAL FUND) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering has submitted Change Order No. (Final) on <br />behalf of Trans Tech Electric, LP, 4601 West Cleveland Road, South Bend, Indiana 46628, <br />indicating the contract amount be decreased by $4,382.00 for a new contract sum, including this <br />Change Order, of $45,462.50. Additionally submitted was the Project Completion Affidavit <br />indicating this new final cost of $45,462.50. Upon a motion made by Mr. Inks, seconded by Mr. <br />Littrell and carried, Change Order No. (Final) and the Project Completion Affidavit were <br />approved subject to the filing of the appropriate three-year Maintenance Bond. <br />APPROVE CHANGE ORDER AND CERTIFICATE OF SUBSTANTIAL COMPLETION <br />CLEVELAND ROAD NORTH WELL FIELD -PROJECT NO. 107-023 (WATER WORKS <br />BOND <br />Mr. Gilot advised that Mr. John Wiltrout, Water Works, has submitted Change Order No.2 on <br />behalf of Casteel Construction Corporation, 23186 West Ireland Road, South Bend, Indiana <br />46614, indicating the Contract amount be increased by $1,863.40 for a new Contract sum, <br />including this Change Order, in the amount of $539,298.40. Additionally submitted was a <br />Certificate for Substantial Completion. Upon a motion made by Mr. Inks, seconded by Mr. <br />Littrell and carried, the Change Order and Certificate for Substantial Completion were approved. <br />APPROVE CHANGE ORDER AND CERTIFICATE OF SUBSTANTIAL COMPLETION <br />SOUTH WELL FIELD TREATMENT PLANT -PROJECT NO. 107-021 (CAPITAL FUND <br />623 <br />Mr. Gilot advised that Mr. John Wiltrout, Water Works, has submitted Change Order No.2 on <br />behalf of Henry-CAP Construction, 1112 Clay Street, Mishawaka, Indiana 46545, indicating the <br />Contract amount be increased by $6,138.63 for a new Contract sum, including this Change <br />Order, in the amount of $1,046,672.63. Additionally submitted was a Certificate for Substantial <br />Completion. Upon a motion made by Mr. Inks, seconded by Mr. Littrell and carried, the Change <br />Order and Certificate for Substantial Completion were approved. <br />