REGULAR MEETING JANUARY 21, 1980
<br />and re- advertise for a vehicle similar to the ones presently being used.
<br />Mr. McMahon asked about the current construction of the ambulances,
<br />and Chief Brassell indicated that they were aluminum models, and
<br />the models specified in the bids were either part or all steel which
<br />considerably reduced its life expectancy versus the all aluminum
<br />models. He indicated that the ambulances were in excellent condition
<br />after four years. Mr. McMahon asked if the Fire Department was
<br />planning to replace the chassis on one of the vehicles, and the
<br />Chief indicated that that was their decision and one more vehicle
<br />would be advertised if the Board approved. Upon a motion made
<br />by Mr. McMahon, seconded by Mr. Kernan, and carried, the bids
<br />received were rejected and permission was granted to re- advertise
<br />the bids and replace the chassis on one of the present vehicles.
<br />AWARD BIDS - ATRIUM PORTION OF FIRST BANK CENTER
<br />Mr. McMahon indicated that Sollitt Construction had recommended the
<br />following bids for award:
<br />Skylight - Bid Package 121
<br />Roper T.B.G. $825,240.00
<br />Award at: 809,640.00
<br />Budget Estimate: 775,000.00
<br />Quarry Tile - Bid Package 118
<br />Interior Finishes, Inc. $137,660.00
<br />Awarded at: 90,925.00
<br />Budget Estimate: 75,000.00
<br />Mechanical - Bid Package 119
<br />Slutsky -Peltz $119,400.00
<br />Awarded at: 119,400.00
<br />Budget Estimate: 160,000.00
<br />Electrical - Bid Package 120
<br />Koontz - Wagner Electric $ 56,500.00
<br />Awarded at: 56,500.00
<br />Budget Estimate: 75,000.00
<br />Mr. McMahon indicated that the total awards amount was $1,076,456
<br />and the budget estimate total was $1,085,000. He further stated
<br />that two of the items, Bid Package 115, Structural Steel, and Bid
<br />Package 117, Curtain. Wall, had come in at excessive and unreasonable
<br />figures. He stated that the budget estimate for the structural steel
<br />package was $255,000, and the bid received was in the amount of
<br />$599,600. The budget estimate for the curtain wall package was
<br />$312,000, and the bid received was in the amount of $938,732. He
<br />explained that further negotiations would be made to try and bring
<br />the costs down and it was recommended that these two bids not be
<br />awarded at this time. He stated that it could be possible the two
<br />items would have to be re- advertised. Upon motion made by Mr.
<br />McMahon, seconded by Mr. Hill and carried, the Board awarded the
<br />bids as recommended, subject to receipt of the required Performance
<br />Bonds and Labor and Material Payment Bonds and the Certificates of
<br />Insurance.
<br />CHANGE ORDER NO. 2 APPROVED - FIRST BANK CENTER PROJECT -
<br />MASS EXCAVATION
<br />A change order in the contract with Ritschard Brothers, Inc. for
<br />mass excavation for the First Bank Center Project was submitted
<br />to the Board, recommended for approval by the Construction Manager
<br />and the Architect. The contract sum was in the amount of $176,550,
<br />and the amount of the change order was an addition of $300,622.07,
<br />for a total cost to date, if approved, of $477,172.07. Mr. McMahon
<br />explained that the contract had been let for the performance of
<br />excavation and backfill work in order to construct the footings
<br />and garage portion. He indicated that a 2% increase to a general
<br />contract was not a great amount; however, it was an 80% increase
<br />in the cost for excavation. He explained that conditions occurred
<br />
|