Dewaterina of Existing Detention Ponds: <br />Sub - contract with Selge Construction Co., Inc. to pump out the remaining water from the <br />existing detention ponds. Selge would accomplish this by setting up a pump near the <br />gates on the south side of the pond and running a HDPE discharge pipe across the pond <br />to the existing manhole. They would also pump the water from the other ponds into the <br />central pond for removal. It is estimated that the work will take 3 to 4 working days, <br />based on an estimate of 1.2 million gallons of water remaining in the existing ponds. All <br />pumping services are weather permitted. <br />Additional Geotechnical Investigation: <br />Upon completion of the dewatering of the existing detention ponds, additional soil <br />sampling will be completed to classify the soils within the existing detention ponds limits. <br />Earth Explorations will continue to be the sub - contractor (from phase 1). <br />Design Services: <br />CBBEL staff will design and prepare final construction documents for the project. All <br />plans and specifications will be prepared in accordance with City Standards and <br />Specifications. <br />Plans will be developed using base sheets provided from the topographic mapping <br />developed in Phase I and Phase II. The project will consider design features to address <br />the requirements of the regulatory agencies involved with this construction. <br />Specifications will be developed utilizing standard specifications and general conditions <br />provided by the City in addition to CBBEL standard specifications. Applicable conflicts <br />will be brought to your attention for your input. <br />It is anticipated that during the progress of this task, CBBEL will meet regularly with the <br />City staff, and other necessary local representatives to discuss the design and project <br />direction. The meetings will attempt to resolve plan elements which may best <br />accomplish project goals prior to initiating final design drawing preparations. A <br />maximum of three (3) meetings have been included in the proposed fee. <br />CBBEL staff will provide an opinion of probable cost based on the final construction <br />plans. This opinion will be based on the judgment of CBBEL engineering staff, <br />supplemented by local construction project history information provided by the City. An <br />itemized list of the estimated quantities or work units required to complete the job will be <br />included. <br />Permits: A Rule 5 permit (IDEM) will be required for this project. CBBEL will prepare <br />the submittal package and required documentation including the publication of legal <br />notice in a local newspaper. The package will be provided to the City for its signature <br />and submittal to IDEM. All permit application fees will be paid as a reimbursable and are <br />included in the reimbursable expense line item listed below. <br />13 Christopher B. Burke Engineering Ltd. City of South Bend: Erskine Detention Pond Relocation Phase 11 2 <br />