Change Order No. 02 <br />Western Avenue Corridor Improvements <br />Project No. 115-097 <br />Revise Section B.3: <br />3. The project will have intermediate completion dates as listed in the tale below for substantial <br />completion: <br />Phase I & II: Kaley Street and Meade Street Sewer and Water Crossings — June 30, 2017 <br />Phase III: South Side Improvements — l.,l�,uy 31, 2917 August 34, 94-7 September 15, 2017 <br />Phase IV: North Side Improvements — September 15. 2017 nnf hnr_ an 2017 October26, 2017 <br />Phase V: Fixtures, Trees, Fencing, and Landscaping — QGtober 1 2 1 � October 31, 2017 <br />a. The project will have an intermediate substantial completion date of June 30, 2017 for <br />storm sewer to be constructed from the intersection of Western Avenue and Kaley Street to <br />its northern connection on Kaley Street and for water crossings at Meade Street and at <br />Kaley Street. A minimum of one travel lane and one parking lane along Western Avenue <br />shall be open to traffic during the lane closure. <br />b. The project will have an intermediate substantial completion date of 44�L ; 28� August <br />31, 2017 September 15, 2017 for construction of curb, sidewalk, roadway, lighting, pavers, <br />and all project elements complete and in -place on the southern side of the roadway <br />centerline except for pavement markings, benches, bike racks, landscaping, and trees. A <br />minimum of one travel lane and one parking lane along Western Avenue shall be open to <br />traffic during the lane closure period. Temporary parking lane closures will be permitted for <br />water service connections. Phase III of the project can occur simultaneously with Phase Il, <br />provided that the contractor maintains a minimum of one travel lane along Western Avenue <br />and submits a revision to the Maintenance of Traffic Plan that is approved by the City prior <br />to construction. <br />c. The project will have an intermediate substantial completion date of September 15, 2017 <br />October 26, 2017 for construction of curb, sidewalk, roadway, lighting, <br />pavers, pavement markings, and all project elements complete and in -place on the north <br />side of the roadway centerline except for benches, bike racks, landscaping, and trees. A <br />minimum of one travel lane and one parking lane along Western Avenue shall be open to <br />traffic during the lane closure period, <br />d. The project will have an intermediate substantial completion date of <br />October 31, 2017 for installation of benches, bike racks, landscaping, fencing, and trees. A <br />minimum of two travel lanes on Western Avenue shall be open to traffic during the lane <br />closure period. <br />LX. PERMEABLE PAVERS <br />Revise Section B. <br />8. The block shall be laid on 1" of No. 11 limestone on INDOT No. 8 coarse aggregate as shown <br />in the plans. The aggregate will be paid for separately. <br />9. A support layer of Tensar BX1100, or approved equal, shall be laid within No. 8 stone at a level <br />8" to 10" below the bottom of the pavers. An additional layer of Tensar BX1100, or approved <br />equal, shall be between the No. 8 aggregate and No. 11 aggregate, approximately 1" below the <br />pavers. abeve4he-aggregate, dire Gtly below the poro ro <br />LXIV. WATER MAIN <br />Add Section B.3.e: <br />3. Services <br />SHEET 3 OF 4 <br />