Change Order No. 26
<br />One- Way to Two -Way Street Conversion
<br />Division B
<br />Project No. 116-001
<br />Remove 42 SYS from Line Item 114: SODDING, NURSERY AND TOPSOIL, -42 SYS
<br />@ $4.30/SYS for a total subtraction of ($180.60).
<br />Add 4 SYS to Line Item 116: BRICK, DECORATIVE, 4 SYS @ $113.00/SYS for a total
<br />addition of $452.00.
<br />Remove 1 EACH from Line Item 257: SIGNAL PEDESTAL FOUNDATION, A, -1 EACH
<br />@ $585.00/EACH for a total subtraction of ($585.00).
<br />Add 23 LFT to Line Item 261: CONDUIT, PVC, 2 IN, SCHEDULE 80, 23 LFT @
<br />$5.20/LFT for a total addition of $119.60.
<br />Add 58 LFT to Line Item 263: CONDUIT, HDPE, 2 IN, SCHEDULE 80, 58 LFT @
<br />$11.30/LFT for a total addition of $655.40.
<br />Add 54 LFT to Line Item 312: NO, 4 WIRE, COPPER, 4 1/C, 54 LFT @ $1.40/LFT for a
<br />total addition of $75.60.
<br />Add 54 LFT to Line Item 313: NO. 6 WIRE, COPPER, 4 1/C, 54 LFT @ $1.10/LFT for a
<br />total addition of $59.40.
<br />SPECIFICATIONS:
<br />NO CHANGE REQUIRED
<br />DRAWINGS:
<br />Project Number 114-035:
<br />SHEET 9 : Revised Sheet; Revised Detail
<br />SHEETS 31, 38, 44, 94, & 95: Revised Sheets; Revised Parking Spaces,
<br />Deleted Sidewalk
<br />SHEET 56: Revised Sheet; Revised Pavement Markings
<br />Project Number 115-019:
<br />SHEETS 13, 49-A, 58, 60, 85, 116, 118, 170-A, 183, 204-A, 220: Deleted
<br />Sheets
<br />SHEETS 13-A, 49-B, 58-A, 60-A, 85-A, 116-A, 118-A, 170-B, 183-A, 204-B,
<br />220-A: Replaced Sheets; Modified Curb Line, Curb Ramp, & Markings
<br />END OF CHANGE ORDER NO. 26