<br />REGULAR MEETING DECEMBER 9, 2002
<br />The Engineering Division had no objection if the alley between Lots 261 and 262 are replaced by
<br />a public ingress/egress easement and accommodation for turning vehicles as proposed in a separate
<br />site plan. Community and Economic Development strongly supports this vacation request. It is an
<br />initial part of the planned development project on the southwest corner of Main and Jefferson. The
<br />Area Plan Commission staff reviewed the petition and believes vacating this alley would pose
<br />several problems. Vacating these alleys would go against a Common Council policy of not creating
<br />dead end alleys. Several parking lots would not have adequate access to their lots. Cross -access
<br />easements would be necessary. Each future development on this block would be forced to create
<br />new curb cuts for any loading and parking areas. Such a practice is opposite to what is desirable in
<br />the downtown area. It appears as though utilities are present in the proposed vacation area. Utility
<br />easements would be necessary. The Police Department and Fire Department have no objections.
<br />Upon a motion made by Mr. Littrell, seconded by Mr. Inks and carried, this alley vacation was
<br />approved, subject to the above comments.
<br />APPROVE CONSTRUCTION CONTRACT - PORTAGE AVENUE SEWER EXTENSION
<br />(TEACHERS CREDIT UNION) - HERRMAN & GOETZ INC - PROJECT NO 102-077
<br />Mr. Gilot advised that in accordance with the quotation awarded on November 25, 2002, to Herrman
<br />& Goetz d/b/a Underground Services, 225 South Lafayette Boulevard, South Bend, Indiana, in the
<br />amount of $43,739.75 for the above referred to project, a Contract in said amount was being
<br />submitted for Board approval. Upon a motion made by Mr. Gilot, seconded by Mr. Littrell and
<br />carried, the Contract was approved and the appropriate Certificate of Insurance and Schedule of
<br />Wages as submitted were filed.
<br />APPROVE CONSTRUCTION CONTRACT -U.S. 31 TRUNK SEWER EXTENSION - YOUNGS
<br />EXCAVATING - PROJECT NO. 102-062
<br />Mr. Gilot advised that in accordance with the quotation awarded on November 12, 2002, to Youngs
<br />Excavating, Inc., Post Office Box 2766, South Bend, Indiana, in the amount of $466,332.00 for the
<br />above referred to project, a Contract in said amount was being submitted for Board approval. Upon
<br />a motion made by Mr. Inks, seconded by Mr. Gilot and carried, the Contract was approved and the
<br />appropriate Certificate of Insurance, Performance Bond and Labor and Materials Payment Bond as
<br />submitted were filed.
<br />APPROVE SERVICE CONTRACT - ENVIRONMENTAL OVERSIGHT DURING TJX
<br />DEMOLITION, GRADING AND DRAINAGE PROJECT - WEAVER BOOS & GORDON OF
<br />MICHIANA, LLC - PROJECT NO. 102-034C
<br />Mr. Gilot stated that the Board is in receipt of a Service Contract between the City of South Bend
<br />and Weaver Boos & Gordon of Michiana, LLC, 630 East Bronson Street, Suite 1, South Bend,
<br />Indiana, for environmental monitoring during site construction. Mr. Gilot noted that the Service
<br />Contract will be satisfied on an hourly basis. Therefore, upon a motion made by Mr. Littrell,
<br />seconded by Mr. Gilot and carried, the Service Contract was approved and executed.
<br />APPROVAL OF SERVICE CONTRACT - WALNUT/EUCLID CONTROL STRUCTURE
<br />IMPROVEMENTS - LAWSON-FISHER ASSOCIATES P.C.
<br />Mr. Gilot stated that the Board is in receipt of a Service Contract between the City of South Bend
<br />and Lawson -Fisher Associates, Inc., 525 West Washington Avenue, South Bend, Indiana, for
<br />engineering services. Mr. Gilot noted that the Contract is in the amount of $23,400.00. Therefore,
<br />upon a motion made by Mr. Littrell, seconded by Mr. Inks and carried, the Service Contract was
<br />approved and executed.
<br />APPROVAL OF SERVICE CONTRACT - ENROLL TJX DEMOLITION INTO THE
<br />VOLUNTARY REMEDIATION PROGRAM - WEAVER BOOS & GORDON - PROJECT NO.
<br />102-034CD
<br />Mr. Gilot stated that the Board is in receipt of a Service Contract between the City of South Bend
<br />and Weaver Boos & Gordon of Michiana, LLC, 630 East Bronson Street, Suite 1, South Bend,
<br />Indiana, for enrollment into the Voluntary Remediation Program for the TJX Demolition Project.
<br />Mr. Gilot noted that the Service Contract is a 50/50 split with the City's portion not to exceed
<br />$200,000.00. Therefore, upon a motion made by Mr. Gilot, seconded by Mr. Inks and carried, the
<br />Service Contract was approved and executed.