REGULAR MEETING JUNE 10, 2025 128
<br />This was the date set for receiving and opening sealed bids for the above referenced project. The
<br />Clerk tendered proof of publication of the Notice in the South Bend Tribune, which was found to
<br />be sufficient. The following Bids were opened and publicly read:
<br />BOWEN ENGINEERING CORPORATION
<br />8802 N. Meridian St.
<br />Indianapolis, IN 46260
<br />Stout@bownenengineering.com; elaine.dabney@bowenengineering.com
<br />Bid was signed by Mr. Doug Stout
<br />Non-Collusion, Non-Discrimination Affidavit Form was completed.
<br />Five percent (5%) Bid Bond was submitted.
<br />Three (3) Forms MWBE-1.0, 2.0, 2.1 were completed.
<br />One (1) of One (1) Addendum(s) Acknowledgement received.
<br />BID:
<br />Base Bid $4,015,000
<br />R. YODER CONSTRUCTION INC.
<br />27453 County Road 150
<br />Nappanee, IN 46550
<br />shelly@ryoderconstruction.com
<br />Bid was signed by Mr. Brad Yoder
<br />Non-Collusion, Non-Discrimination Affidavit Form was completed.
<br />Five percent (5%) Bid Bond was submitted.
<br />Three (3) Forms MWBE-1.0, 2.0, 2.1 were incomplete.
<br />One (1) of One (1) Addendum(s) Acknowledgement received.
<br />BID:
<br />Base Bid Total $3,670,297
<br />Upon a motion made by VP Molnar, seconded by Ms. Micou and carried by roll call, the above
<br />bids were referred to Public Works for review and recommendation.
<br />AWARD BID AND APPROVE CONTRACT – 2025 COMMUNITY CROSSINGS – PROJECT
<br />NO. 125-004 (PR-00040469)
<br />Leslie Biek, Engineering, advised the Board that on May 27, 2025, bids were received and opened
<br />for the above referenced project. After reviewing those bids, Ms. Biek recommended that the
<br />Board award the contract to the lowest responsive and responsible bidder, Milestone Contractors,
<br />L.P., in the amount of $2,138,000, Divisions 1 & 2, plus Alternates 1 & 2. Therefore, VP Molnar
<br />made a motion that the recommendation be accepted, and the bid be awarded, and the contract
<br />approved as outlined above. Ms. Micou seconded the motion, which carried by roll call.
<br />AWARD BID AND APPROVE CONTRACT – 2025 CURB AND SIDEWALK PROGRAM –
<br />PROJECT NO. 125-001 (PR-00041142)
<br />Gemma Staton, Engineering, advised the Board that on June 10, 2025, bids were received and
<br />opened for the above referenced project. After reviewing those bids, Ms. Staton recommended that
<br />the Board award the contract to the lowest responsive and responsible bidder, Selge Construction
<br />Co., Inc., in the amount of $1,364,781.90; Base Bid Plus Alternates 1 &2. Therefore, VP Molnar
<br />made a motion that the recommendation be accepted, and the bid be awarded, and the contract
<br />approved as outlined above. Ms. Micou seconded the motion, which carried by roll call.
<br />AWARD BID AND APPROVE CONTRACT – VPA LEEPER TENNIS COURTS
<br />RECONSTRUCTION – PROJECT NO. 124-022 (Parks & Recreation)
<br />Lidya Abreha, Engineering, advised the Board that on May 13, 2025, bids were received and
<br />opened for the above referenced project. After reviewing those bids, Ms. Abreha recommended
<br />that the Board award the contract to the lowest responsive and responsible bidder, Byrne & Jones
<br />Construction, in the amount of $1,756,171.07, Base Bid Division A. Therefore, VP Molnar made
<br />a motion that the recommendation be accepted, and the bid be awarded, and the contract approved
<br />as outlined above. Ms. Micou seconded the motion, which carried by roll call.
<br />APPROVE CHANGE ORDER NO. 2 – SEWER AND MANHOLE REHABILITATION –
<br />PROJECT NO. 122-019 (PO-0013623)
|