REGULAR MEETING JANUARY 22, 2019 16 <br />APPROVE CHANGE ORDER NO. 3 — FIRE STATION NO. 9 — PROJECT NO. 116-012 <br />(2018 FIRE STATION NO. 9 CAPITAL) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 3 on behalf <br />of Ziolkowski Construction, Inc., 4050 Ralph Jones Drive, South Bend, IN 46628, indicating the <br />contract amount be increased by $8,219 for a new contract sum, including this Change Order, in <br />the amount of $3,667,859. Upon a motion made by Ms. Maradik, seconded by Ms. O'Sullivan <br />and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NOS. 6 AND 7 — ERSKINE CLUBHOUSE RENOVATION — <br />PROJECT NO. 116-108 (VPA MAINTENANCE FUND) <br />Mr. Gilot advised that Mr. Kyle Silveus, Engineering, has submitted the below Change Orders <br />on behalf of Ziolkowski Construction, Inc., 4050 Ralph Jones Drive, South Bend, IN 46628: <br />a) Change Order No.: 6 <br />(1) Increase Amount: $62,958 <br />(2) Percent of Increase: 6.81 % <br />(3) Total Percent of Change: 8.84% <br />(4) Revised Contract Amount: $987,142 <br />b) Change Order No.: 7 <br />(1) Increase Amount: $2,984 <br />(2) Percent of Increase: 0.3% <br />(3) Total Percent of Change: 9.16% <br />(4) Revised Contract Amount: $990,126 <br />Upon a motion made by Ms. Maradik, seconded by Ms. O'Sullivan and carried, the Change <br />Orders were approved. <br />APPROVE CHANGE ORDER NO. 4 — VENUES PARKS AND ARTS MAINTENANCE <br />STORAGE BUILDING — PROJECT NO. 118-046R (PARK BOND SERIES I) <br />Mr. Gilot advised that Ms. Alicia Czarnecki, Engineering, has submitted Change Order No. 4 on <br />behalf of The Robert Henry Corporation, 404 S. Frances St., South Bend, IN 46624, indicating <br />the contract amount be increased by $1,490 for a new contract sum, including this Change Order, <br />in the amount of $389,380. Upon a motion made by Ms. Maradik, seconded by Ms. O'Sullivan <br />and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 (FINAL) AND PROJECT COMPLETION AFFIDAVIT <br />— NAVARRE STREET MILLING AND ASPHALT OVERLAY — PROJECT NO 117-128 <br />(LRSA/STREET MAINTENANCE <br />Mr. Gilot advised that Mr. Toy Villa, Engineering has submitted Change Order No. 1 (Final) on <br />behalf of Walsh & Kelly, Inc., 24358 SR 23, South Bend, IN 46614 indicating the contract <br />amount be increased by $7,000, plus an additional one -hundred ninety-five (195) days, for a new <br />contract sum, including this Change Order, of $49,503.50 and a revised project completion date <br />of December 12, 2018. Additionally submitted was the Project Completion Affidavit indicating <br />this new final cost of $49,503.50. Upon a motion made by Ms. Maradik, seconded by Ms. <br />O'Sullivan and carried, Change Order No. 1 (Final) and the Project Completion Affidavit were <br />approved. <br />APPROVE CHANGE ORDER NO. 3 (FINAL) AND PROJECT COMPLETION AFFIDAVIT <br />— RAVINA PARK -BOWMAN CREEK STABILIZATION — PROJECT NO. 117-073A <br />(SPECIAL LOIT/MAJOR PROJECTS) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering has submitted Change Order No. 3 (Final) on <br />behalf of Williams Creek Management Corporation, 4620 S. County Road 600 East, Plainfield, <br />IL 46168 indicating the contract amount be decreased by $3,125.30 for a new contract sum, <br />including this Change Order, of $246,143.70. Additionally submitted was the Project <br />Completion Affidavit indicating this new final cost of $246,143.70. Upon a motion made by Ms. <br />Maradik, seconded by Ms. O'Sullivan and carried, Change Order No. 3 (Final) and the Project <br />Completion Affidavit were approved. <br />APPROVE CHANGE ORDER NO. 1 (FINAL) AND PROJECT COMPLETION AFFIDAVIT <br />— 2018 STREET PAVING — PROJECT NO 118-070 (BUILDING AND STREET <br />MAINTENANCE) - <br />