Section 4.2, the Architect shall prepare Change Orders and Construction Change Directives for the Owner's
<br />approval and execution in accordance with the Contract Documents.
<br />§ 3.6.5.2 The Architect shall maintain records relative to changes in the Work.
<br />§ 3.6.6 Project Completion
<br />§ 3.6.6.1 The Architect shall:
<br />A conduct inspections to determine tile date or dates Of Substantial Completion and the date of final
<br />completion;
<br />.2 issue Certificates of Substantial Completion;
<br />.3 forward to, the Owner, for the Owner's review and records, written warranties and related documents
<br />required by the Contract Documents and received from the Contractor; and,
<br />.4 issue a final Certificate for Payment based upon a final inspection indicating that, to the best of the
<br />Architect's knowledge, information, and belief, the Work complies with the requirements of tile
<br />Contract Documents.
<br />§ 3.6.6.2 The Architect's inspections shall be conducted with the Owner to check conformance of the Work with the
<br />requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the
<br />Contractor of Work to be completed or corrected.
<br />§ 3.6.6.3 When Substantial Completion has been achieved, the Architect shall inform the Owner about the balance of
<br />the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if
<br />any, for final completion or correction of the Work.
<br />§ 3.6.6.4 The Architect shall forward to tile Owner the following information received from the Contractor: (1)
<br />consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2)
<br />affidavits, receipts, releases and waivers of Hens, or bonds indemnifying the Owner against liens; and (3) any other
<br />documentation required of the Contractor tinder the Contract Documents.
<br />§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion,
<br />the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility
<br />operations and performance.
<br />ARTICLE 4 SUPPLEMENTAL AND ADDITIONAL SERVICES
<br />§ 41 Supplemental Services
<br />§ 4.1.1 The services listed below are not included in Basic Services but may be required for the Project. The
<br />Architect shall provide the listed Supplemental Services only if specifically designated in the table below as the
<br />Architect's responsibility, and the Owner shall compensate the Architect as provided in Section 11.2. Unless
<br />otherwise specifically addressed in this Agreement, if neither the Owner not- the Architect is designated, the parties
<br />agree that the listed Supplemental Service is not being provided for the Project.
<br />(Desigynate the Architect's Supl)1ementalServices awl the atwers Sul)lVeniental Services required,for the Project
<br />Pry indicating whether- the Architect or Owner shall be responsible.for 1j)-oviding the identr fled SupplemenialService.
<br />Insert a description of the Sul)plemental Services in Section 4.1.2 below orallach the description q1'services as an
<br />exhibit to this Agreement)
<br />Supplemental Services
<br />Responsibility
<br />(Architect, Owner, or not 1))-ovided)
<br />§ 4A.1.1 Programming
<br />4,1,12 Multiple preliminary designs
<br />4.1.1.3 Measured drawings
<br />§ 4.1.1.4 Existing facilities surveys
<br />§ 4, 1 A.5 Site evaluation and planning
<br />§ 4.1.1.6 Building Information Model management
<br />responsibilities
<br />§4,1,1,7 Development of Building Information Models for
<br />post construction use
<br />AIA DocumeintBIOITM —2017, Copyright@ 1974, 1978, 1987, 1997, 2007 and 2017 by The Arnedcan Institute of Architects, All rights reserved. WAIRMN(k
<br />Un[t. "Ms MAII IDunn nineint 'Vs protected by U.S, Colpyrrqht Law and MtwnaflonM'rrea0e& Unauthorized ruproduction ordMrMuflon of thus MAII Document, 12
<br />or any poMon of it, rnay resuft ht severe clyfl and criminall, pe"Mdes, and WH be rrospolitied to Hie maXh71UT11 extent possflbie under the A", This
<br />docurnent was produced by AIA software at 12:60:46 on 01/16/2018 under order No. 2731703659 which expires on 01116/2019, and is not for resale.
<br />user Notes: (389ADAIC)
<br />
|