Construction Services <br />11-21-16 <br />Re: Finish date extension <br />Mr. Estes, <br />We are requesting an extension of the completion date, for the Stair Tower project, at the <br />JMS Building. <br />We request it be extended from December 23rd 2016 to January 6th 2017. <br />The steel fabricator has indicated to us, that they can not have the steel stairs to us by the <br />original scheduled install date of December 6th. They believe they can have it onsite on <br />December 13th. We will lose 6 working days (Saturday included) <br />Another reason is that we lost some time between the board approval and the pre- <br />constrcution meeting. Since we were not allowed to start until we had our pre -con <br />meeting, it cost us 8 working days. (Saturday's included) <br />We will lose a total of 14 working days (Saturdays included), before the steel stairs even <br />arrive onsite. <br />We are working 10 hour days 6 days a week to meet the schedule. But, believe we will fall <br />short on meeting the December 23rd completion day, due to the reason mentioned above. <br />Thank you for your time <br />Ty Heckaman <br />HGR Construction Services <br />