Laserfiche WebLink
EXHIBIT E <br />WHIT Construction Schedule <br />Planning & Design Phase (12/2005 - 10/2008) <br />• Purchase of property <br />• Architect/Engineering Fees <br />• Legg] fees <br />Construction Phase (11/2008 - 3/201(1) <br />• Phase I (3/2009 - 7/2009) <br />- New Main Entrance & Foyer <br />- New Exterior Window System <br />- Roof Repairs <br />- Jumbotron <br />• Phase II (3/009 - 9/2009) <br />- First Floor Interior Renovations <br />• Phase 111 (5/2009 - 1 112009) <br />- Second Floor Interior Renovations <br />• Phase IV (10/2009 - 12!2009) <br />- Basement Renovations <br />Equipment Phase (9/2009 - 2/2010) <br />• Digital Backbone <br />• Master Control <br />• Remote Broadcast System <br />Move-In Phase (2/2010 - 3/2010) <br />• Moving Expenses <br />• Furniture <br />Patie 9 of 12 <br />