Laserfiche WebLink
15Morris Performing Arts Center Parking Garage <br />Garmong Construction <br />Preliminary Parking Garage Schedule <br />ID Task Name Duration Start Finish <br />3 Preconstruction & Design Phase 240 days Mon 4/6/26 Fri 3/5/27 <br />4 Schematic Design 60 days Mon 4/6/26 Fri 6/26/26 <br />5 SD Budget 15 days Mon 6/29/26 Fri 7/17/26 <br />6 Design Development (DDs)60 days Mon 7/20/26 Fri 10/9/26 <br />7 DD Budget 20 days Mon 10/12/26 Fri 11/6/26 <br />8 Construction Documents - Design 45 days Mon 11/9/26 Fri 1/8/27 <br />10 State CDR 20 days Mon 1/11/27 Fri 2/5/27 <br />9 Local Permitting 20 days Mon 2/8/27 Fri 3/5/27 <br />11 Bidding Phase 40 days Mon 1/11/27 Fri 3/5/27 <br />12 Bidding/Procurement 30 days Mon 1/11/27 Fri 2/19/27 <br />13 GMP Development & Finalization 10 days Mon 2/22/27 Fri 3/5/27 <br />14 Long-Lead Procurement & Submittals Phase 145 days Mon 3/8/27 Fri 9/24/27 <br />25 Construction Phase 295 days Mon 4/5/27 Fri 5/19/28 <br />26 Site 290 days Mon 4/5/27 Fri 5/12/28 <br />34 Building 245 days Mon 6/14/27 Fri 5/19/28 <br />1 Owner PR Items 10 days Mon 4/26/27 Fri 5/7/27 <br />2 Ground Breaking 10 days Mon 4/26/27 Fri 5/7/27 <br />54 Turnover 0 days Fri 5/19/28 Fri 5/19/28 <br />55 Turnover to Developer 0 days Fri 5/19/28 Fri 5/19/28 <br />Preconstruction & Design Phase <br />Schematic Design <br />SD Budget <br />Design Development (DDs) <br />DD Budget <br />Construction Documents - Design <br />State CDR <br />Local Permitting <br />Bidding Phase <br />Bidding/Procurement <br />GMP Development & Finalization <br />Long-Lead Procurement & Submittals Phase <br />Construction Phase <br />Site <br />Building <br />Owner PR Items <br />Ground Breaking <br />Turnover <br />Turnover to Developer <br />Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 12026202720282029 <br />City of South Bend Morris Performing Arts CenterParking Garage <br />Page 1 of 1