Laserfiche WebLink
c. Apply/Submit for IDEM Construction Permit for Public Water System-327 IAC 8-3-3 <br />A1.06 90% Final Design Plans <br />A. Advise Owner of any adjustments to the opinion of probable Construction after acceptance by <br />Owner of the 50% Preliminary Design Phase documents, revised opinion of probable Construction <br />Cost as determined in the Preliminary Design Phase, and any other deliverables subject to any <br />Owner -directed modifications and/or changes in the scope, extent, character, and/or design <br />requirements for the Project, and upon written authorization from Owner, Engineer shall: <br />1. Prepare final Drawings and Specifications indicating the scope, extent, and character of the <br />work to be performed and furnished by Contractor. <br />2. Provide detailed Construction Cost Estimates to Owner. <br />3. Prepare and furnish electronic review copies of the bidding documents for review by <br />Owner, its legal counsel, and other advisors, and assist Owner in the preparation of other <br />related documents within 180 days of authorization to proceed by the Owner. Within <br />10 calendar days of receipt, Owner shall submit to Engineer any comments and, subject <br />to the provisions of Paragraph 6.0l.G, instructions for revisions. <br />4. Revise the bidding documents in accordance with comments and instructions from the <br />Owner, as appropriate, and submit electronic final copies of the bidding documents, a <br />revised Construction Cost Estimate, and any other deliverables to Owner within 7 <br />calendar days after receipt of Owner's comments and instructions. <br />5. Submission of 90% plans to City will be made within calendar days from the date of City's <br />notice to proceed. <br />B. Engineer's services under the 100% Final Design Plans will be considered complete on the date <br />when the submittals required by Paragraph A1.03.A.5 have been delivered to and approved by <br />Owner. <br />1. Tentative project schedule could be as follows, <br />Notice to Proceed ............................................. <br />August 2, 2025 <br />50% Preliminary Design Plans Submittal .................. <br />December 12, 2025 <br />90% Final Design Plans Submittal .......................... <br />February 13, 2026 <br />100% Final Design Plans Complete ........................ <br />February 27, 2026 <br />Project Bid ...................................................... <br />March 17, 2026 <br />Project Award .................................................. <br />April 14, 2026 <br />Project Construction Complete .............................. <br />September 11, 2026 <br />A 1.07 Bidding or Negotiating Phase <br />A. After acceptance by Owner of the bidding documents and the most recent opinion of probable <br />Construction Cost as determined in the Final Design Plans, and upon written authorization by <br />Owner to proceed, Engineer shall: <br />Page 6 <br />(Exhibit A — Engineer's Services) <br />EJCDC E-500 Agreement Between Owner and Engineer for Professional Services <br />Copyright © 2008 National Society of Professional Engineers for EJCDC. All rights reserved. <br />