Scope of Work: <br />• Layout of work in the basement— Foreman 3 Hours <br />• Remove dirt out of hole cored by Larson -Danielson, remove dirt from basement - Journeyman - 8 Hours <br />• Set sump pit, pump, floats and stub discharge pipe out —Journeyman - 4 Hours <br />• Set and anchor fiberglass lid — Journeyman - 4 Hours <br />• Install trim for sump pump package (i.e. check valve, ball valve) — Journeyman - 2 Hours <br />• Layout of core through foundation and route of piping — Foreman 3 Hour <br />• Dig trench to grade to ensure proper pitch, bed/install piping, seal pipe penetrations through foundation, <br />backfill and compact trench —Journeyman — 64 hours <br />• Tie 2" PVC into vertical down spout —Journeyman — 4 Hours <br />