BID TABULATION
<br />2024 Community Crossings Round 2
<br />Project No: 124-047
<br />For Bids Due: November 12, 2024
<br />DIVISION 1: BENDIX DRIVE FROM 350FT NORTH OF CLEVELAND RD TO PORTAGE AVE
<br />Item No.Description Quantity Unit Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br />1 Maintenace of Traffic 1 LS 15,280.00$ 15,280.00$ 9,646.00$ 9,646.00$ 15,200.00$ 15,200.00$
<br />2 Mobilization and Demobilization 1 LS 10,910.00$ 10,910.00$ 6,293.65$ 6,293.65$ 9,661.35$ 9,661.35$
<br />3 Construction Engineering (1.5%)1 LS 3,270.00$ 3,270.00$ 3,500.00$ 3,500.00$ 3,183.10$ 3,183.10$
<br />4 Milling, 4 in.2,748 SYS 4.25$ 11,679.00$ 3.65$ 10,030.20$ 4.80$ 13,190.40$
<br />5 Excavation, Common 481 CYS 52.00$ 25,012.00$ 20.00$ 9,620.00$ 58.00$ 27,898.00$
<br />6 Subgrade Treatment Type II 1,325 SYS 25.00$ 33,125.00$ 22.00$ 29,150.00$ 10.30$ 13,647.50$
<br />7 HMA Surface, Type C 328 TON 85.00$ 27,880.00$ 105.00$ 34,440.00$ 103.00$ 33,784.00$
<br />8 HMA Intermediate, Type B 547 TON 72.00$ 39,384.00$ 95.00$ 51,965.00$ 86.00$ 47,042.00$
<br />9 HMA Base, Type B 291 TON 70.00$ 20,370.00$ 90.00$ 26,190.00$ 93.00$ 27,063.00$
<br />10 Tack Coat 1 TON 1.50$ 1.50$ 624.00$ 624.00$ 2,200.00$ 2,200.00$
<br />11 Joint Adhesive, Surface 970 LFT 0.10$ 97.00$ 0.50$ 485.00$ 1.00$ 970.00$
<br />12 Joint Adhesive, Intermediate 970 LFT 0.10$ 97.00$ 0.50$ 485.00$ 1.00$ 970.00$
<br />13 PCCP for Approaches, 9 in.48 SYS 130.00$ 6,240.00$ 120.00$ 5,760.00$ 126.00$ 6,048.00$
<br />14 Manhole, Structure Adjustment 1 EA 500.00$ 500.00$ 800.00$ 800.00$ 1,400.00$ 1,400.00$
<br />15 Inlet, J10 1 EA 5,500.00$ 5,500.00$ 3,700.00$ 3,700.00$ 4,100.00$ 4,100.00$
<br />16 Pipe, Type 2, Circular, 12 in.113 LFT 125.00$ 14,125.00$ 100.00$ 11,300.00$ 102.00$ 11,526.00$
<br />17 Line, Thermoplastic, Solid, Yellow, 4 IN.1,437 LFT 0.80$ 1,149.60$ 1.05$ 1,508.85$ 1.05$ 1,508.85$
<br />18 Line, Thermoplastic, Solid, White, 4 IN.840 LFT 0.80$ 672.00$ 1.05$ 882.00$ 1.05$ 882.00$
<br />19 Line, Thermoplastic, Broken, White, 4 IN.716 LFT 0.65$ 465.40$ 1.05$ 751.80$ 1.05$ 751.80$
<br />20 Grooving for Pavement Markings 3,233 LFT 1.30$ 4,202.90$ 0.55$ 1,778.15$ 0.55$ 1,778.15$
<br />21 Transverse Marking, Thermoplastic, Stop Line, 24 IN.63 LFT 16.00$ 1,008.00$ 8.95$ 563.85$ 8.95$ 563.85$
<br />22 Pavement Message Marking, Thermoplastic, Lane Indication Arrow 3 EA 250.00$ 750.00$ 125.00$ 375.00$ 125.00$ 375.00$
<br />23 Pavement Message Marking, Thermoplastic, Lane Indication Arrow, Turn and Through 3 EA 250.00$ 750.00$ 125.00$ 375.00$ 125.00$ 375.00$
<br />24 Detector Housing, Replace 1 EA 1,800.00$ 1,800.00$ 1,969.00$ 1,969.00$ 1,969.00$ 1,969.00$
<br />25 Traffic Loop 6 EA 200.00$ 1,200.00$ 828.00$ 4,968.00$ 828.00$ 4,968.00$
<br />26 Curb and Gutter, Type B, Concrete 500 LFT 40.00$ 20,000.00$ 54.00$ 27,000.00$ 52.00$ 26,000.00$
<br />27 Sodding, Nursery 142 SYS 5.00$ 710.00$ 15.25$ 2,165.50$ 36.00$ 5,112.00$
<br />28 Topsoil 16 CYS 140.00$ 2,240.00$ 75.00$ 1,200.00$ 75.00$ 1,200.00$
<br />29 Inspection Hole, Deeper than 3-ft 6 EA 2,000.00$ 12,000.00$ 340.00$ 2,040.00$ 1,270.00$ 7,620.00$
<br />30 Inspection Hole, 3-ft Deep or Less 10 EA 1,500.00$ 15,000.00$ 308.00$ 3,080.00$ 805.00$ 8,050.00$
<br />31 Inlet, C15 2 EA 6,000.00$ 12,000.00$ 6,000.00$ 12,000.00$ 4,600.00$ 9,200.00$
<br />287,418.40$ 264,646.00$ 288,237.00$
<br />DIVISION 2: JEFFERSON BOULEVARD FROM CHICAGO ST TO FALCON ST
<br />Item No.Description Quantity Unit Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br />1 Maintenace of Traffic 1 LS 18,260.00$ 18,260.00$ 4,068.00$ 4,068.00$ 11,200.00$ 11,200.00$
<br />2 Mobilization and Demobilization 1 LS 13,040.00$ 13,040.00$ 1,821.60$ 1,821.60$ 10,600.00$ 10,600.00$
<br />3 Construction Engineering (1.5%)1 LS 3,910.00$ 3,910.00$ 4,000.00$ 4,000.00$ 1,415.30$ 1,415.30$
<br />4 Milling, 4 in.4,131 SYS 4.25$ 17,556.75$ 4.65$ 19,209.15$ 5.70$ 23,546.70$
<br />5 HMA Surface, TYPE B 341 TON 82.00$ 27,962.00$ 92.00$ 31,372.00$ 99.00$ 33,759.00$
<br />6 HMA Intermediate, Type B 568 TON 72.00$ 40,896.00$ 82.00$ 46,576.00$ 85.00$ 48,280.00$
<br />7 Tack Coat 1 TON 1.50$ 1.50$ 624.00$ 624.00$ 2,500.00$ 2,500.00$
<br />8 Joint Adhesive, Surface 1,352 LFT 0.10$ 135.20$ 0.50$ 676.00$ 1.00$ 1,352.00$
<br />9 Joint Adhesive, Intermediate 1,352 LFT 0.10$ 135.20$ 0.50$ 676.00$ 1.00$ 1,352.00$
<br />10 Manhole, Structure Adjustment 4 EA 500.00$ 2,000.00$ 800.00$ 3,200.00$ 1,100.00$ 4,400.00$
<br />11 Inlet, Structure Adjustment 2 EA 500.00$ 1,000.00$ 600.00$ 1,200.00$ 900.00$ 1,800.00$
<br />12 Sidewalk, Concrete 144 SYS 220.00$ 31,680.00$ 100.00$ 14,400.00$ 148.00$ 21,312.00$
<br />13 Curb Ramp, Concrete 132 SYS 320.00$ 42,240.00$ 280.00$ 36,960.00$ 233.00$ 30,756.00$
<br />14 Standard Curb 2,316 LFT 35.00$ 81,060.00$ 54.00$ 125,064.00$ 55.00$ 127,380.00$
<br />15 Sodding, Nursery 249 SYS 5.00$ 1,245.00$ 15.25$ 3,797.25$ 25.00$ 6,225.00$
<br />16 Topsoil 28 CYS 140.00$ 3,920.00$ 75.00$ 2,100.00$ 75.00$ 2,100.00$
<br />17 Inspection Hole, Deeper than 3-ft 4 EA 2,000.00$ 8,000.00$ 340.00$ 1,360.00$ 1,270.00$ 5,080.00$
<br />18 Inspection Hole, 3-ft Deep or Less 2 EA 1,500.00$ 3,000.00$ 308.00$ 616.00$ 805.00$ 1,610.00$
<br />296,041.65$ 297,720.00$ 334,668.00$
<br />DIVISION 3: N. LEE COURT FROM CUL-DE-SAC TO FAIRFAX AVE
<br />Item No.Description Quantity Unit Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br />1 Maintenace of Traffic 1 LS 17,810.00$ 17,810.00$ 2,144.00$ 2,144.00$ 3,800.00$ 3,800.00$
<br />2 Mobilization and Demobilization 1 LS 12,720.00$ 12,720.00$ 7,681.75$ 7,681.75$ 7,500.00$ 7,500.00$
<br />3 Construction Engineering (1.5%)1 LS 3,820.00$ 3,820.00$ 3,000.00$ 3,000.00$ 1,424.40$ 1,424.40$
<br />4 Excavation, Common 451 CYS 52.00$ 23,452.00$ 20.00$ 9,020.00$ 66.00$ 29,766.00$
<br />5 Subgrade Treatment Type II 1,159 SYS 25.00$ 28,975.00$ 22.00$ 25,498.00$ 10.40$ 12,053.60$
<br />6 HMA Surface, TYPE B 96 TON 82.00$ 7,872.00$ 105.00$ 10,080.00$ 117.00$ 11,232.00$
<br />7 HMA Intermediate, Type B 159 TON 72.00$ 11,448.00$ 95.00$ 15,105.00$ 98.00$ 15,582.00$
<br />8 HMA Base, Type B 255 TON 70.00$ 17,850.00$ 90.00$ 22,950.00$ 89.00$ 22,695.00$
<br />9 Tack Coat 1 TON 1.50$ 1.50$ 624.00$ 624.00$ 1.00$ 1.00$
<br />10 Joint Adhesive, Surface 299 LFT 0.10$ 29.90$ 0.50$ 149.50$ 1.00$ 299.00$
<br />11 Joint Adhesive, Intermediate 299 LFT 0.10$ 29.90$ 0.50$ 149.50$ 1.00$ 299.00$
<br />12 PCCP for Approaches, 6 in.68 SYS 130.00$ 8,840.00$ 114.00$ 7,752.00$ 183.00$ 12,444.00$
<br />13 Manhole, Structure Adjustment 1 EA 500.00$ 500.00$ 800.00$ 800.00$ 1,100.00$ 1,100.00$
<br />14 Water Valve, Structure Adjustment 1 EA 300.00$ 300.00$ 300.00$ 300.00$ 280.00$ 280.00$
<br />15 Inlet, J10 1 EA 5,500.00$ 5,500.00$ 3,700.00$ 3,700.00$ 4,300.00$ 4,300.00$
<br />16 Pipe, Type 2, Circular, 12 in.247 LFT 125.00$ 30,875.00$ 100.00$ 24,700.00$ 64.00$ 15,808.00$
<br />17 Sidewalk, Concrete 174 SYS 220.00$ 38,280.00$ 90.00$ 15,660.00$ 120.00$ 20,880.00$
<br />18 Curb Ramp, Concrete 11 SYS 320.00$ 3,520.00$ 400.00$ 4,400.00$ 500.00$ 5,500.00$
<br />Rieth Riley Construction Co., Inc. Milestone Contractors North, Inc.
<br />Rieth Riley Construction Co., Inc. Milestone Contractors North, Inc.
<br />Rieth Riley Construction Co., Inc. Milestone Contractors North, Inc.
<br />DIVISION 1 TOTAL
<br />Engineer's Estimate
<br />Engineer's Estimate
<br />DIVISION 2 TOTAL
<br />Engineer's Estimate
<br />Page 1 of 2
|