IDTask ModeTask Name Duration Start Finish Predecessors Resource Names1Contract1 dayTue 7/9/24Tue 7/9/242Topographic Survey45 daysWed 7/10/24Fri 8/23/2413Utility Coordination279 daysWed 7/10/24Mon 4/14/254Initial Notice40 daysWed 7/10/24Sun 8/18/2415Verification and Conflict Analysis Letter40 daysThu 12/26/24Mon 2/3/254,2,116Work Plan40 daysTue 2/4/25Sat 3/15/2557Relocations, If Necessary30 daysSun 3/16/25Mon 4/14/2568Construction Documents209 daysSat 8/24/24Thu 3/20/25930% Design50 daysSat 8/24/24Sat 10/12/24210City Review14 daysSun 10/13/24Sat 10/26/2491160% Plans and Estimate60 daysSun 10/27/24Wed 12/25/242,1012City Review14 daysThu 12/26/24Wed 1/8/25111390% Plans, Specs, Estimate45 daysThu 1/9/25Sat 2/22/251214City Review14 daysSun 2/23/25Sat 3/8/251315Final Plans, Sepcs and Estimate12 daysSun 3/9/25Thu 3/20/251416Geotechnical Investigation60 daysSun 10/13/24Wed 12/11/24917Bid Period19 daysFri 3/21/25Tue 4/8/2518Advertisement1 dayFri 3/21/25Fri 3/21/2515,1619Advertisement1 dayFri 3/28/25Fri 3/28/2518FS+6 days20Bid Opening1 dayTue 4/8/25Tue 4/8/2519FS+10 days21Bid Award1 dayTue 4/22/25Tue 4/22/2520FS+13 days22Construction180 daysTue 5/6/25Sat 11/1/2521FS+13 daysMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTJun 30, '24Jul 7, '24Jul 14, '24Jul 21, '24Jul 28, '24Aug 4, '24Aug 11, '24Aug 18, '24Aug 25, '24Sep 1, '24Sep 8, '24Sep 15, '24Sep 22, '24Sep 29, '24Oct 6, '24Oct 13, '24Oct 20, '24Oct 27, '24Nov 3, '24Nov 10, '24Nov 17, '24Nov 24, '24Dec 1, '24Dec 8, '24Dec 15, '24Dec 22, '24Dec 29, '24Jan 5, '25Jan 12, '25Jan 19, '25Jan 26, '25Feb 2, '25Feb 9, '25Feb 16, '25Feb 23, '25Mar 2, '25Mar 9, '25Mar 16, '25Mar 23, '25Mar 30, '25Apr 6, '25Apr 13, '25Apr 20, '25Apr 27, '25May 4, '25May 11, '25TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 1Project: Greenlawn Avenue andDate: Wed 6/26/24