IDTask ModeTask Name Duration Start Finish Predecessors Resource Names1Contract1 dayTue 7/9/24Tue 7/9/242Topographic Survey21 daysWed 7/10/24Tue 7/30/2413Utility Coordination114 daysWed 7/10/24Thu 10/31/244Initial Notice14 daysWed 7/10/24Tue 7/23/2415Verification and Conflict Analysis and Work Plan Letter35 daysWed 8/28/24Tue 10/1/244,2,106Relocations, If Necessary30 daysWed 10/2/24Thu 10/31/2457Construction Documents100 daysWed 7/10/24Thu 10/17/248Conceptual Design14 daysWed 7/10/24Tue 7/23/2419City Review14 daysWed 7/24/24Tue 8/6/2481060% Plans and Estimate21 daysWed 8/7/24Tue 8/27/242,911City Review14 daysWed 8/28/24Tue 9/10/24101290% Plans, Specs, Estimate21 daysWed 9/11/24Tue 10/1/241113City Review10 daysWed 10/2/24Fri 10/11/241214Final Plans, Sepcs and Estimate6 daysSat 10/12/24Thu 10/17/241315Asbestos Investigation60 daysWed 7/10/24Sat 9/7/24116Bid Period19 daysFri 10/18/24Tue 11/5/2417Advertisement1 dayFri 10/18/24Fri 10/18/2414,1518Advertisement1 dayFri 10/25/24Fri 10/25/2417FS+6 days19Bid Opening1 dayTue 11/5/24Tue 11/5/2418FS+10 days20Bid Award1 dayTue 11/19/24Tue 11/19/2419FS+13 days21Construction45 daysTue 12/3/24Thu 1/16/2520FS+13 daysMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMJun 30, '24Jul 7, '24Jul 14, '24Jul 21, '24Jul 28, '24Aug 4, '24Aug 11, '24Aug 18, '24Aug 25, '24Sep 1, '24Sep 8, '24Sep 15, '24Sep 22, '24Sep 29, '24Oct 6, '24Oct 13, '24Oct 20, '24Oct 27, '24Nov 3, '24Nov 10, '24Nov 17, '24Nov 24, '24Dec 1, '24Dec 8, '24Dec 15, '24TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 1Project: Potawatomi Park Pool DDate: Wed 6/26/24