consultants, and for approval of submissions by authorities having jurisdiction over the Project. Once approved by
<br />the Owner, time limits established by the schedule shall not, except for reasonable cause, be exceeded by the
<br />Architect or Owner. With the Owner's approval, the Architect shall adjust the schedule, if necessary, as the Project
<br />proceeds until the commencement of constmction.
<br />§ 3.1.4 The Architect shall submit information to the Construction Manager and participate in developing and
<br />revising the Project schedule as it relates to the Architect's services. The Architect shall review and approve, or take
<br />other appropriate action upon, the portion of the Project schedule relating to the performance of the Architect's
<br />services.
<br />§ 3.1.5 The Architect shall not be responsible for an Owner's directive or substitution, or for the Owner's acceptance
<br />of non -conforming work, made or given without the Architect's written approval.
<br />§ 3.1.6 The Architect shall, in coordination with the Construction Manager, contact governments] authorities
<br />required to approve the Construction Documents and entities providing utility services to the Project. The Architect
<br />shall respond to applicable design requirements imposed by those authorities and entities.
<br />§ 3.1.7 The Architect shall assist the Owner and Construction Manager in connection with the Owner's responsibility
<br />for filing documents required for the approval of governmental authorities having jurisdiction over the Project.
<br />§ 3.1.8 Prior to the Owner's acceptance of the Construction Manager's Guaranteed Maximum Price proposal, or the
<br />Owner's approval of the Construction Manager's Control Estimate, as applicable, the Architect shall consider the
<br />Construction Manager's requests for substitutions and, upon written request of the Construction Manager, provide
<br />clarification or interpretations pertaining to the Drawings, Specifications, and other documents submitted by the
<br />Architect. The Architect and Construction Manager shall include the Owner in communications related to
<br />substitution requests, clarifications, and interpretations.
<br />§ 3.2 Review of the Construction Manager's Guaranteed Maximum Price Proposal or Control Estimate
<br />§ 3.2.1 At a time to be mutually agreed upon by the Owner and the Construction Manager, the Construction Manager
<br />shall prepare, for review by the Owner and Architect, and for the Owner's acceptance or approval, a Guaranteed
<br />Maximum Price proposal or Control Estimate. The Architect shall assist the Owner in reviewing the Construction
<br />Manager's proposal or estimate. The Architect's review is not for the purpose of discovering errors, omissions, or
<br />inconsistencies; for the assumption of any responsibility for the Construction Manager's proposed means, methods,
<br />sequences, techniques, or procedures; or for the verification of any estimates of cost or estimated cost proposals. In
<br />the event that the Architect discovers any inconsistencies or inaccuracies in the information presented, the Architect
<br />shall promptly notify the Owner and Construction Manager.
<br />§ 3.2.2 Upon authorization by the Owner, and subject to Section 4.2.1.14, the Architect shall update the Drawings,
<br />Specifications, and other documents to incorporate the agreed upon assumptions and clarifications contained in the
<br />Guaranteed Maximum Price Amendment or Control Estimate.
<br />§ 3.3 Schematic Design Phase Services
<br />§ 3.3.1 The Architect shall review the program, and other information famished by the Owner and Construction
<br />Manager, and shall review laws, codes, and regulations applicable to the Architect's services.
<br />§ 3.3.2 The Architect shall prepare a preliminary evaluation of the Owner's program, schedule, budget for the Cost
<br />of the Work, Project site, and other Initial Information, each in terms of the other, to ascertain the requirements of
<br />the Project. The Architect shall notify the Owner of (I) any inconsistencies discovered in the information, and (2)
<br />other information or consulting services that may be reasonably needed for the Project.
<br />§ 3.3.3 The Architect shall present its preliminary evaluation to the Owner and Construction Manager and shall
<br />discuss with the Owner and Construction Manager alternative approaches to design and construction of the Project
<br />The Architect shall reach an understanding with the Owner regarding the requirements of the Project.
<br />§ 3.3.4 Based on the Project requirements agreed upon with the Owner, the Architect shall prepare and present, to the
<br />Owner and Construction Manager, for the Owner's approval, a preliminary design illustrating the scale and
<br />relationship of the Project components.
<br />Init. AIADoament B133-2019.Copyd9ht02014, and 2019. All rights rexrvel.'The American Intl teof Aterhooda'Amerlcan Institute ofArchilecta;'AIA; the
<br />AIA Logo, and "AIA Contract Documents' are trademarks of The Admitted Institute of Architects. This document was produced at 11:3e:41 ET on 00I3012o23 7
<br />under Oder No.211444405e which expires on art M24, is not for regale, is licensed for one-time use only, and may only be usetl in accordance with the AIA
<br />( Contmet Documents®Terme of Service. To report copyd9M wolations, email docinfc®eiaronlractecom.
<br />Deer Names: (3139AM46)
<br />
|