Activity IDActivity NameOriginalDurationStartFinishFC1520Install Auger Support Piles1013-Mar-2526-Mar-25FC1170Install New 36" Influent Pipe/Replace Slab1527-Mar-2516-Apr-25FC1180Modify RAS Piping/Replace Slab827-Mar-2507-Apr-25FC1190FRP Slab at Influent 36" Piping117-Apr-2517-Apr-25FC1200FRP Influent Box Walls1518-Apr-2508-May-25FC1210Repair Existing Concrete Walls, Cracks, and Anchors2018-Apr-2515-May-25FC1220FRP Concrete Launder Troughs and Walls2009-May-2506-Jun-25FC1230Grout Fill at Bottom of Clarifier Tank1016-May-2530-May-25FC1240CLSM Fill & Top Slab at Existing Conc Troughs523-May-2530-May-25FC1250Install Protective Slurry Mortar1002-Jun-2513-Jun-25FC1260Install New Clarifier Equipment2016-Jun-2514-Jul-25FC1270Install New Clarifier Bridge1030-Jun-2514-Jul-25FC1280Install New Effluent Baffles1008-Jul-2521-Jul-25FC1290Install New Handrail and Grating515-Jul-2521-Jul-25FC1300Rough In Electrical Conduit and Wiring1515-Jul-2504-Aug-25FC1310Install Clarifier Controls and Instruments1515-Jul-2504-Aug-25FC1320Install New Clarifier Influent Gate529-Jul-2504-Aug-25FC1330Electrical Terminations, Fixtures, and Testing1005-Aug-2518-Aug-25Final Clarifier 3Final Clarifier 313613-Mar-2523-Sep-25DemolitionDemolition2513-Mar-2516-Apr-25DFC1120Disconnect/Remove Electrical Conduit/Connections513-Mar-2519-Mar-25DFC1130Remove Existing Clarifier Equipment520-Mar-2526-Mar-25DFC1140Remove Existing Handrail & Grating527-Mar-2502-Apr-25DFC1150Remove Existing Fillet Concrete1027-Mar-2509-Apr-25DFC1160Sawcut Bottom Slab for New 36" Influent Pipe510-Apr-2516-Apr-25DFC1170Sawcut Slab for RAS Piping510-Apr-2516-Apr-25New ConstructionNew Construction11117-Apr-2523-Sep-25FC1530Install Auger Support Piles1017-Apr-2530-Apr-25FC1340Install New 36" Influent Pipe/Replace Slab1501-May-2521-May-25FC1350Modify RAS Piping/Replace Slab801-May-2512-May-25FC1360FRP Slab at Influent 36" Piping122-May-2522-May-25FC1370FRP Influent Box Walls1523-May-2513-Jun-25FC1380Repair Existing Concrete Walls, Cracks, and Anchors2023-May-2520-Jun-25FC1390FRP Concrete Launder Troughs and Walls2016-Jun-2514-Jul-25FC1400Grout Fill at Bottom of Clarifier Tank1023-Jun-2507-Jul-25FC1410CLSM Fill & Top Slab at Existing Conc Troughs530-Jun-2507-Jul-25FC1420Install Protective Slurry Mortar1008-Jul-2521-Jul-25FC1430Install New Clarifier Equipment2022-Jul-2518-Aug-25FC1440Install New Clarifier Bridge1005-Aug-2518-Aug-25FC1450Install New Effluent Baffles1012-Aug-2525-Aug-25FC1460Install New Handrail and Grating519-Aug-2525-Aug-25FC1470Rough In Electrical Conduit and Wiring1519-Aug-2509-Sep-25FC1480Install Clarifier Controls and Instruments1519-Aug-2509-Sep-25FC1490Install New Clarifier Influent Gate503-Sep-2509-Sep-25FC1500Electrical Terminations, Fixtures, and Testing1010-Sep-2523-Sep-25RAS Flow Meter ReplacementRAS Flow Meter Replacement16804-Mar-2528-Oct-25R1000Remove/Replace RAS Flow Meter 1504-Mar-2510-Mar-25R1010Remove/Replace RAS Flow Meter 2508-Apr-2514-Apr-25R1020Remove/Replace RAS Flow Meter 3513-May-2519-May-25R1040LOTO Clarifier 4 and Drain315-Oct-2517-Oct-25R1030Remove/Replace RAS Flow Meter 4520-Oct-2524-Oct-25R1050Place Clarifier 4 Back into Service227-Oct-2528-Oct-25AllowancesAllowances0ContingencyContingency0Customer ChangesCustomer Changes0Retired ActivitiesRetired Activities012001230122011200122011201123012201120112301220112001230122011200122012201120012201120012001230122011200122012201123012201120012301220112001200122011201123012201120012301July 2023ASONDJFMApril 2024May 2024JJuly 2024ASONDJFMApril 2025May 2025JJuly 2025ASONDJFMApril 2026May 2026JJuly 2026ASInstall Auger Support PilesInstall New 36" Influent Pipe/Replace SlabModify RAS Piping/Replace SlabFRP Slab at Influent 36" PipingFRP Influent Box WallsRepair Existing Concrete Walls, Cracks, and AnchorsFRP Concrete Launder Troughs and WallsGrout Fill at Bottom of Clarifier TankCLSM Fill & Top Slab at Existing Conc TroughsInstall Protective Slurry MortarInstall New Clarifier EquipmentInstall New Clarifier BridgeInstall New Effluent BafflesInstall New Handrail and GratingRough In Electrical Conduit and WiringInstall Clarifier Controls and InstrumentsInstall New Clarifier Influent GateElectrical Terminations, Fixtures, and Testing23-Sep-25, Final Clarifier 316-Apr-25, DemolitionDisconnect/Remove Electrical Conduit/ConnectionsRemove Existing Clarifier EquipmentRemove Existing Handrail & GratingRemove Existing Fillet ConcreteSawcut Bottom Slab for New 36" Influent PipeSawcut Slab for RAS Piping23-Sep-25, New ConstructionInstall Auger Support PilesInstall New 36" Influent Pipe/Replace SlabModify RAS Piping/Replace SlabFRP Slab at Influent 36" PipingFRP Influent Box WallsRepair Existing Concrete Walls, Cracks, and AnchorsFRP Concrete Launder Troughs and WallsGrout Fill at Bottom of Clarifier TankCLSM Fill & Top Slab at Existing Conc TroughsInstall Protective Slurry MortarInstall New Clarifier EquipmentInstall New Clarifier BridgeInstall New Effluent BafflesInstall New Handrail and GratingRough In Electrical Conduit and WiringInstall Clarifier Controls and InstrumentsInstall New Clarifier Influent GateElectrical Terminations, Fixtures, and Testing28-Oct-25, RAS Flow Meter ReplacementRemove/Replace RAS Flow Meter 1Remove/Replace RAS Flow Meter 2Remove/Replace RAS Flow Meter 3LOTO Clarifier 4 and DrainRemove/Replace RAS Flow Meter 4Place Clarifier 4 Back into ServiceSouth Bend WWTP EQ Basin Clarifier ProjectHID23058Primary Baseline View10-Jul-23 13:45Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryPage 5 of 5TASK filters: In Progress, Not Started.© Oracle Corporation