BOWEN <br />Precast Production <br />6-8 Weeks <br />Offsite <br />From start offabrication <br />Can run concurrently with Base Slab Installation <br />Base Slab Install/Cure <br />4-6 Weeks <br />Onsite <br />From Dutchland mobilization to site <br />Can run concurrently with Precast Production <br />Precast Installation <br />1 Week <br />Onsite <br />Installation to commence once fabrication is <br />complete <br />Tension/Grout/Seal <br />3-5 Weeks <br />Onsite <br />Tank ready for leak -test <br />Structure <br />Please let us know if you would like to further explore any of these items. <br />Sincerely, <br />Ken Sullivan <br />Regional Sales Manager <br />Dutchland LLC <br />