4 <br /> <br />95% Detailed Design Services & Easement Assistance September – October 2023 <br />95% Design Review Workshop October 2023 <br /> Final Detailed Design Services November 2023 <br /> Permit Assistance November 2023 – January 2024 <br /> Bidding Phase November – December 2023 <br /> Construction Engineering Phase* January – December 2024 <br /> <br /> *Assume delayed start waiting for materials. <br /> <br />E. BUDGET <br /> <br />Task 1: Workshops and Project Management $ 8,879 (Lump Sum) <br />Task 2: Field Work $ 9,030 (Lump Sum) <br />Task 3: 50% Detailed Design Services $ 35,601 (Lump Sum) <br />Task 4: 95% Detailed Design Services $ 30,571 (Lump Sum) <br />Task 5: Final Design Services $ 8,347 (Lump Sum) <br />Task 6: Permit Assistance $ 5,171 (Lump Sum) <br />Task 7: Easement Assistance (Allowance) $ 5,000 (Hourly) 1 <br />Task 8: Bidding Phase $ 8,160 (Hourly) 1 <br />Task 9: Construction Engineering Phase $ 34,706 (Hourly) 1 <br /> SUM: $ 145,465 <br />1 In accordance with the rate schedule in Section G. <br /> <br />F. EXCEPTIONS <br /> <br />Upon separate written authorization by the CITY and after approval of negotiated fees, ENGINEER can provide <br />additional services such as those listed below. <br /> <br />· Additional easement preparation beyond the scoped easement description. <br />· Additional permitting beyond the scoped permits. (i.e. Erosion Control) <br />· Contaminated soil testing and / or groundwater monitoring. <br />· Subsurface utility engineering. <br />· Wetland mitigation and/or restoration plans. <br />· Phase I environmental assessment. <br />· Additional workshops, meetings, or site visits beyond the scope. <br />· Resident Project Representative. <br />· Conformed to contract drawings. <br />· Post construction monitoring. <br />· Operation & Maintenance Manual. <br />· Green / sustainable infrastructure design. <br />· Asset Management Plan. <br />· Record drawings. <br />· Confined entry surveying of the existing structure for record drawing confirmation. <br />· Collection hydraulic modeling to confirm pipe size diameters. (i.e. SWMM) <br />· Contractor pay application, AIS, final completion review and/or processing. <br /> <br />