Laserfiche WebLink
BID TABULATION#122‐044#122-044 - 2022 Curb and Sidewalk Round 2DIV 1Item No. Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost 1 CONCRETE SIDEWALK, REMOVE 495 SY $ 35.00 $ 17,325.00 $ 45.00 $ 22,275.00 43.00$ $ 21,285.00 $ 73.50 $ 36,382.50 $ 54.15 $ 26,804.25 2 CONCRETE SIDEWALK, 4-IN 500 SY $ 60.00 $ 30,000.00 $ 86.00 $ 43,000.00 $ 77.00 $ 38,500.00 $ 100.75 $ 50,375.00 $ 70.60 $ 35,300.00 3 CONCRETE CURB, REMOVE 855 LF $ 20.00 $ 17,100.00 $ 25.00 $ 21,375.00 $ 32.00 $ 27,360.00 $ 32.75 $ 28,001.25 $ 31.85 $ 27,231.75 4 CONCRETE CURB, MODIFIED 1130 LF $ 45.00 $ 50,850.00 $ 66.00 $ 74,580.00 $ 68.00 $ 76,840.00 $ 52.25 $ 59,042.50 $ 75.15 $ 84,919.50 5 CONCRETE APPROACH, REMOVE 80 SY $ 50.00 $ 4,000.00 $ 50.00 $ 4,000.00 $ 80.00 $ 6,400.00 $ 65.00 $ 5,200.00 $ 64.50 $ 5,160.00 6 PCCP FOR APPROACHES, 6-IN 55 SY $ 90.00 $ 4,950.00 $ 125.00 $ 6,875.00 $ 110.00 $ 6,050.00 $ 151.00 $ 8,305.00 $ 129.20 $ 7,106.00 7 CURB RAMP, REMOVE 30 SY $ 75.00 $ 2,250.00 $ 150.00 $ 4,500.00 $ 90.00 $ 2,700.00 $ 65.00 $ 1,950.00 $ 229.35 $ 6,880.50 8 ONE-WAY PERPENDICULAR CURB RAMP 20 SY $ 200.00 $ 4,000.00 $ 325.00 $ 6,500.00 $ 195.00 $ 3,900.00 $ 247.00 $ 4,940.00 $ 283.90 $ 5,678.00 9 PAIRED PERPENDICULAR CURB RAMP 15 SY $ 200.00 $ 3,000.00 $ 325.00 $ 4,875.00 $ 195.00 $ 2,925.00 $ 262.00 $ 3,930.00 $ 280.40 $ 4,206.00 10 TOPSOIL AND SEEDING 645 SY $ 30.00 $ 19,350.00 $ 45.00 $ 29,025.00 $ 27.00 $ 17,415.00 $ 29.45 $ 18,995.25 $ 47.35 $ 30,540.75 11 TREE, REMOVE, 18-IN 1 EA $ 1,000.00 $ 1,000.00 $ 1,275.00 $ 1,275.00 $ 700.00 $ 700.00 $ 625.00 $ 625.00 $ 600.00 $ 600.00 12 TREE, REMOVE, 30-IN 2 EA $ 1,400.00 $ 2,800.00 $ 2,475.00 $ 4,950.00 $ 2,000.00 $ 4,000.00 $ 1,850.00 $ 3,700.00 $ 3,610.10 $ 7,220.20 13 PLANT, DECIDUOUS TREE, SINGLE STEM, 2-IN TO 2.5-IN2 EA $ 1,000.00 $ 2,000.00 $ 1,525.00 $ 3,050.00 $ 1,550.00 $ 3,100.00 $ 1,525.00 $ 3,050.00 $ 1,525.00 $ 3,050.00 DIV 1 Total $ 158,625.00 $ 226,280.00 $ 211,175.00 $ 224,496.50 $ 244,696.95 DIV 2Item No. Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost 1 CONCRETE SIDEWALK, REMOVE 125 SY $ 35.00 $ 4,375.00 $ 85.00 $ 10,625.00 $ 50.00 $ 6,250.00 $ 96.40 $ 12,050.00 $ 85.80 $ 10,725.00 2 CONCRETE SIDEWALK, 4-IN 100 SY $ 60.00 $ 6,000.00 $ 121.00 $ 12,100.00 $ 75.00 $ 7,500.00 $ 142.25 $ 14,225.00 $ 79.35 $ 7,935.00 3 CONCRETE CURB, REMOVE 200 LF $ 20.00 $ 4,000.00 $ 30.00 $ 6,000.00 $ 35.00 $ 7,000.00 $ 57.00 $ 11,400.00 $ 38.40 $ 7,680.00 4 CONCRETE CURB, MODIFIED 200 LF $ 45.00 $ 9,000.00 $ 86.00 $ 17,200.00 $ 65.00 $ 13,000.00 $ 64.75 $ 12,950.00 $ 92.45 $ 18,490.00 5 CURB RAMP, REMOVE 50 SY $ 75.00 $ 3,750.00 $ 160.00 $ 8,000.00 $ 120.00 $ 6,000.00 $ 80.00 $ 4,000.00 $ 258.05 $ 12,902.50 6 PAIRED PERPENDICULAR CURB RAMP 50 SY $ 200.00 $ 10,000.00 $ 340.00 $ 17,000.00 $ 320.00 $ 16,000.00 $ 298.00 $ 14,900.00 $ 338.75 $ 16,937.50 7 TOPSOIL AND SEEDING 135 SY $ 30.00 $ 4,050.00 $ 60.00 $ 8,100.00 $ 45.00 $ 6,075.00 $ 45.45 $ 6,135.75 $ 52.30 $ 7,060.50 8 PLANT, DECIDUOUS TREE, SINGLE STEM, 2-IN TO 2.5-IN1 EA $ 1,000.00 $ 1,000.00 $ 2,055.00 $ 2,055.00 $ 2,200.00 $ 2,200.00 $ 2,055.00 $ 2,055.00 $ 2,055.00 $ 2,055.00 DIV 2 Total $ 42,175.00 $ 81,080.00 $ 64,025.00 $ 77,715.75 $ 83,785.50 DIV 3Item No. Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost 1 CONCRETE SIDEWALK, REMOVE 680 SY $ 35.00 $ 23,800.00 $ 45.00 $ 30,600.00 $ 43.00 $ 29,240.00 $ 70.35 $ 47,838.00 $ 47.10 $ 32,028.00 2 CONCRETE SIDEWALK, 4-IN 685 SY $ 60.00 $ 41,100.00 $ 80.00 $ 54,800.00 $ 77.00 $ 52,745.00 $ 64.25 $ 44,011.25 $ 72.65 $ 49,765.25 3 CONCRETE CURB, REMOVE 1270 LF $ 20.00 $ 25,400.00 $ 30.00 $ 38,100.00 $ 25.00 $ 31,750.00 $ 38.00 $ 48,260.00 $ 31.80 $ 40,386.00 4 CONCRETE CURB, MODIFIED 1270 LF $ 45.00 $ 57,150.00 $ 65.00 $ 82,550.00 $ 63.00 $ 80,010.00 $ 38.10 $ 48,387.00 $ 70.90 $ 90,043.00 5 CONCRETE APPROACH, REMOVE 70 SY $ 50.00 $ 3,500.00 $ 65.00 $ 4,550.00 $ 80.00 $ 5,600.00 $ 60.00 $ 4,200.00 $ 73.75 $ 5,162.50 6 GRAVEL APPROACH, REMOVE 40 SY $ 30.00 $ 1,200.00 $ 65.00 $ 2,600.00 $ 125.00 $ 5,000.00 $ 15.00 $ 600.00 $ 64.50 $ 2,580.00 7 PCCP FOR APPROACHES, 6-IN 85 SY $ 90.00 $ 7,650.00 $ 120.00 $ 10,200.00 $ 125.00 $ 10,625.00 $ 140.00 $ 11,900.00 $ 140.70 $ 11,959.50 8 TOPSOIL AND SEEDING 925 SY $ 30.00 $ 27,750.00 $ 35.00 $ 32,375.00 $ 25.00 $ 23,125.00 $ 21.75 $ 20,118.75 $ 45.80 $ 42,365.00 9 TREE, REMOVE, 30-IN 6 EA $ 1,400.00 $ 8,400.00 $ 2,450.00 $ 14,700.00 $ 2,000.00 $ 12,000.00 $ 1,800.00 $ 10,800.00 $ 2,424.15 $ 14,544.90 10 STUMP, REMOVE 2 EA $ 500.00 $ 1,000.00 $ 900.00 $ 1,800.00 $ 400.00 $ 800.00 $ 350.00 $ 700.00 $ 300.00 $ 600.00 11 PLANT, DECIDUOUS TREE, SINGLE STEM, 2-IN TO 2.5-IN13 EA $ 1,000.00 $ 13,000.00 $ 2,055.00 $ 26,715.00 $ 1,000.00 $ 13,000.00 $ 970.00 $ 12,610.00 $ 970.00 $ 12,610.00 DIV 3 Total $ 209,950.00 $ 298,990.00 $ 263,895.00 $ 249,425.00 $ 302,044.15 Premium Concrete ServicesEngineer's Estimate Milestone Contractors North Selge Construction Rieth-Riley ConstructionSelge Construction Rieth-Riley ConstructionSelge Construction Rieth-Riley Construction Engineer's Estimate Milestone Contractors North Premium Concrete Services Engineer's Estimate Milestone Contractors North Premium Concrete ServicesS:\Public Works\Projects\Projects by Year\2022 Projects\122‐044 2022 Curb and Sidewalk Round 2\1 ‐ Admin\1 ‐ BPW Documents\Bid Tab 122‐044 received 20221213