Page 3
<br />(Exhibit A – Engineer’s Services)
<br />EJCDC E-500 Agreement Between Owner and Engineer for Professional Services
<br />Copyright © 2008 National Society of Professional Engineers for EJCDC. All rights reserved.
<br />g.Perform design survey in sufficient detail to obtain topographic data, utilities,
<br />buildings, walls, walks, signs, vaults, and natural and man-made features, as evidenced
<br />by facilities at the ground surface and marks by others, necessary for the development
<br />of project plans, including all potentially affected trees, 6 inches in diameter and
<br />greater, identified by size.
<br />h.Take cross sections at specified intervals across the right-of-way of public roadways
<br />and or the project limits (as described above) whichever is further out. Additional cross
<br />sections shall be taken at intersection of streets, roads, railroads, driveways, etc. Obtain
<br />elevations of all existing structures such as drainage culverts, utilities and other
<br />structures. Spot elevation data will be provided at:
<br />i.Indicate spot elevations at all finish floors, at each threshold, building edges, insets and
<br />projections, exterior platforms, steps (top and bottom treads), corners, building
<br />entrances, break in grade, ramps, area ways, tree grates, etc. within the project limits,
<br />and at top and bottom of curb.
<br />j.Provide a listing of all symbols, notations and legends used in the field survey. VS
<br />shall furnish a hard copy together with all field survey information collected on
<br />electronic media. VS shall also prepare master drawings (1-foot contours) from data
<br />collected in topographic survey using AutoCAD Civil 3D and shall submit a hard copy
<br />together with electronic format. VS shall delineate and label the location of all
<br />buildings, structures, fences, railings, signs, walls, walks, paved areas, curbs and other
<br />permanent structures and existing improvements. VS shall outline all building edges,
<br />insets and projections, and below grade structures such as vaults, basements, and
<br />areaways where applicable, as evidenced by facilities at the ground surface and marks
<br />by others.
<br />Assumptions
<br />1)Subsurface utility engineering is not included in this proposal.
<br />2)If private utilities (not part of Indiana811) are present, locates will be contracted
<br />and paid for by others, if required.
<br />7.Furnish 2 review copies of the plans and any other deliverables to Owner within 90
<br />calendar days of the Effective Date and review it with Owner. Within 21 calendar days of
<br />receipt, Owner shall submit to Engineer any comments regarding the plans and any other
<br />deliverables. This will be the 30% Design Submittal Milestone.
<br />8.Revise the plans and any other deliverables in response to Owner’s comments, as
<br />appropriate, and furnish 2 copies of the revised Report and any other deliverables to the
<br />Owner within 7 calendar days of receipt of Owner’s comments.
<br />9.The CONSULTANT shall prepare a conceptual streetscape design and final landscape
<br />planting design improvements that will be incorporated into the final Linden Avenue
<br />design documents. Conceptual Design shall include geometric design layout drawings on
<br />aerial photography in order to represent existing features along with the proposed
|