DEPARTMENT OF PUBLIC WORKS
<br /> DIVISION OF ENGINEERING
<br /> FINAL COMPARISON OF ESTIMATES
<br /> CONTRACT VS FINAL
<br /> Contractor: Rieth-Riley Construction Co., Inc. Project No. 121-008
<br /> Project Name:
<br /> 2021 Roadway Reconstruction
<br /> No. ITEMS Quantity Placed
<br /> Over/
<br />Under UNIT UNIT PRICE EXTENSION
<br /> 55 Inlet, Clean Existing 4 0 -4 EACH $1,102.23 -$4,408.92
<br /> 56 Patching Concrete Structures 60 10 -50 SFT $75.00 -$3,750.00
<br /> 57 Manhole, Type A, 4' Dia., Type 1 Frame, Closed Lid 5 5 0 EACH $5,750.00 $0.00
<br /> 58 Manhole Adjust to Grade 6 14 8 EACH $480.00 $3,840.00
<br /> 59 Adjust Water Valve to Grade 1 9 8 EACH $400.00 $3,200.00
<br /> 60 Adjust Inlet to Grade 21 9 -12 EACH $480.00 -$5,760.00
<br /> 61 Removing Manholes 5 5 0 EACH $750.00 $0.00
<br /> 62 12 IN. Diameter Gravity Sanitary Sewer (8-10 FT Deep) 619 574 -45 LFT $84.00 -$3,780.00
<br /> 63 18 IN. Diameter Gravity Sanitary Sewer (10-20 FT Deep) 87 79 -8 LFT $259.00 -$2,072.00
<br /> 64 Bypass Pumping 5 5 0 EACH $5,000.00 $0.00
<br /> 65 Sewer Service Reinstatement 25 22 -3 EACH $1,550.00 -$4,650.00
<br /> 66 Traffic Loop Replacement 6 6 0 EACH $150.00 $0.00
<br /> 67 Traffic Detector Housing Replacement 1 1 0 EACH $1,500.00 $0.00
<br /> 68 Line, Thermoplastic, Solid, White, 4 IN. 94 76 -18 LFT $1.25 -$22.50
<br /> 69 Line, Thermoplastic, Solid, Yellow, 4 IN. 358 320 -38 LFT $0.95 -$36.10
<br /> 70 Transverse Marking, Thermoplastic, Stop Line, White, 24 IN. 165 123 -42 LFT $6.95 -$291.90
<br /> 71
<br /> Transverse Marking, Thermoplastic, Crosswalk Line, White,
<br />6 IN. 882 757 -125 LFT $1.75 -$218.75
<br /> 72
<br /> Transverse Message Marking, Thermoplastic, Lane
<br />Indication Arrow 2 2 0 EACH $100.00 $0.00
<br /> 73
<br /> Transverse Marking, Multi-Component, Stop Line, White, 24
<br />IN. 22 19 -3 LFT $45.00 -$135.00
<br /> 74
<br /> Transverse Marking, Multi-Component, Crosswalk Line,
<br />White, 6 IN. 43 47 4 LFT $25.00 $100.00
<br /> 75 CO#1 - 12.5mm HAC 702 666.82 -35.18 TON $81.00 -$2,849.58
<br /> 76 CO#1 - Calvert Tree Removal & Traffic Control 1 1 0 LSUM $10,417.95 $0.00
<br /> 77 CO#1 - Jefferson Tree Removal 1 1 0 LSUM $10,829.47 $0.00
<br /> 78 CO#1 - Traffic Control on Poland 1 1 0 LSUM $2,722.53 $0.00
<br /> 79 CO#1 - Additional T&M on Hancock due to gas line conflict. 1 1 0 LSUM $6,375.21 $0.00
<br /> 80 CO#1 - Poland St. Unknown Structure & Debris Removal. 1 1 0 LSUM $3,450.00 $0.00
<br /> 81
<br /> CO#2 - Additional T&M on Hancock due to gas line conflict
<br />2022. 1 1 0 LSUM $7,326.33 $0.00
<br /> 82 0 0 $0.00
<br /> 83 0 0 $0.00
<br /> 84 0 0 $0.00
<br /> 85 0 0 $0.00
<br /> Contract + Approved Change Orders $69,047.33
|