BID TABULATION
<br />Morris Performing Arts Center - Main Level Slab Replacement
<br />Project No: 121-029A
<br />Project Title
<br />Item No. Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost
<br />1
<br />Complete demolition, including: walls (full and partial), doors/windows, concrete step, ceiling systems,
<br />electrical, and mechanical components as noted on the demolition drawings.1 LS $26,750.00 $26,750.00 $29,575.00 $29,575.00 $40,000 $40,000.00
<br />2
<br />New wall infill, new ceiling, and new finishes throughout Box Office Lobby and Box Office (including
<br />paint; trim at walls, openings and columns; installation of in-stock CPT1; floor leveling at CT2 transition
<br />to match existing ramp condition; SS1 at storefront bay ledges)1 LS $93,000.00 $93,000.00 $150,047.00 $150,047.00 $235,600.00 $235,600.00
<br />3 New exterior storefront Box Office window systems (including countertop at office desk)1 LS $23,600.00 $23,600.00 $17,162.00 $17,162.00 $15,000.00 $15,000.00
<br />4 New interior Box Office Window system (including countertop and surrounding trim)1 LS $18,000.00 $18,000.00 $44,027.00 $44,027.00 $35,000.00 $35,000.00
<br />5 Mechanical work as required in Box Office Lobby (not limited to: rerouting ductwork as necessary, etc.) 1 LS $5,500.00 $5,500.00 $19,556.00 $19,556.00 $10,000.00 $10,000.00
<br />6
<br />Electrical renovations as required in the Box Office Lobby and Box Office (not limited to relocating
<br />wiring and access panel, light fixture replacements, etc.)1 LS $22,800.00 $22,800.00 $23,196.00 $23,196.00 $25,000.00 $25,000.00Total$189,650.00 $283,563.00 $360,600.00
<br />I hereby certify that the above truly and accurately represents bids received for this project on July 26, 2022.
<br />Becca Plantz, Project Engineer
<br />The Robert Henry Corp.
<br />Y
<br />Engineer's Estimate Larson Danielson Construction Co., Inc.
<br />Non-Collusion Affadavit Y
<br />S:\Public Works\Projects\Projects by Year\2021 Projects\121-029 Morris Performing Arts Center 100-Yr\1 - Admin\1 - BPW Documents\Box Office\Bid Tabulation 121-029C
|