BID/PROPOSAL
<br />CITY OF SOUTH BEND
<br />Project Name: 2021 Curb and Sidewalk Contruction _ _ cj
<br />Project Number: 121-001 =
<br />For Bids Due: June 8, 2021 at 9:00am Local Time to �{ s
<br />Contractor Name: Milestone Contractors North, Inc. �baR
<br />DIVISION B3
<br />Item No.
<br />Description
<br />Quanti
<br />Unit Unit Price
<br />Total Amount
<br />1
<br />CONCRETE SIDEWALK, REMOVE
<br />240
<br />SYS $
<br />45.00
<br />$
<br />10,800.00
<br />2
<br />CONCRETE SIDEWALK. 4 -IN
<br />240
<br />SYS $
<br />60.00
<br />65.00
<br />14 400.00
<br />3
<br />CONCRETE CURB REMOVE
<br />145
<br />LFT $
<br />25.00
<br />$
<br />3,625.00
<br />4
<br />CONCRETE CURB, MODIFIED
<br />145
<br />LFT $
<br />60.00
<br />$
<br />8,700.00
<br />7
<br />TOPSOIL AND SEEDING
<br />80
<br />SYS $
<br />40.00
<br />$
<br />3,200.00
<br />8
<br />TREE. REMOVE, 6 IN
<br />1
<br />EA $
<br />200.00
<br />$
<br />200.00
<br />9
<br />TREE, REMOVE, 10 IN
<br />1
<br />EA $
<br />400.00
<br />$
<br />400.00
<br />10
<br />TREE. REMOVE, 18 IN
<br />1
<br />EA
<br />800.00
<br />$
<br />800.00
<br />13
<br />STUMP REMOVE
<br />1
<br />EA
<br />200.00
<br />125.00
<br />200.00
<br />14
<br />PLANT, DECIDUOUS TREE, SINGLE STEM, 2 -IN
<br />TO 2.5 IN
<br />4
<br />$
<br />EA
<br />1,045.00
<br />$
<br />4,180.00
<br />15
<br />CURB RAMP, REMOVE
<br />10
<br />SYS $
<br />150.00
<br />$
<br />1,500.00
<br />16
<br />ONE-WAY PERPENDICULAR CURB RAMP
<br />10
<br />1 SYS $
<br />300.00
<br />$
<br />3.000.00
<br />$
<br />1,705.00
<br />16
<br />ONE-WAY PERPENDICULAR CURB RAMP
<br />DIVISION B
<br />$
<br />51,005.00
<br />DIVISION C1
<br />Item No.
<br />Description
<br />Quantity
<br />Unit
<br />Unit Price
<br />Total Amount
<br />1
<br />CONCRETE SIDEWALK, REMOVE
<br />240
<br />SYS $
<br />55.00
<br />$
<br />13,200.00
<br />2
<br />CONCRETE SIDEWAL 4 -IN
<br />240
<br />SYS $
<br />65.00
<br />$
<br />15.600.00
<br />3
<br />CONCRETE CURB. REMOVE
<br />405
<br />LFT $
<br />20.00
<br />$
<br />8,100.00
<br />4
<br />CONCRETE CURB, MODIFIED
<br />405
<br />LFT $
<br />40.00
<br />$
<br />16,200.00
<br />7
<br />TOPSOIL AND SEEDING
<br />225
<br />SYS $
<br />35.00
<br />$
<br />7,875.00
<br />10
<br />TREE, REMOVE, 18 IN
<br />2
<br />EA $
<br />600.00
<br />$
<br />1,200.00
<br />11
<br />TREE, REMOVE, 30 IN
<br />1
<br />EA $
<br />2,000.00
<br />$
<br />2,000.00
<br />14
<br />PLANT, DECIDUOUS TREE, SINGLE STEM, 2 -IN
<br />TO 2.5 IN
<br />3
<br />$
<br />EA
<br />1,195.00
<br />$
<br />3,585.00
<br />15
<br />CURB RAMP. REMOVE
<br />16
<br />SYS $
<br />125.00
<br />$
<br />2,000.00
<br />17
<br />PAIRED PERPENDICULAR CURB RAMP
<br />16
<br />SYS $
<br />195.00
<br />$
<br />3,120.00
<br />200.00
<br />14
<br />PLANT, DECIDUOUS TREE, SINGLE STEM, 2 -IN
<br />TO 2.5 IN
<br />3
<br />DIVISION C
<br />$
<br />72,880.00
<br />DIVISION D1
<br />Item No.
<br />Description
<br />Quantity
<br />Unit
<br />Unit Price
<br />Total Amount
<br />1
<br />CONCRETE SIDEWALK REMOVE
<br />425
<br />SYS $
<br />40.00
<br />$
<br />17 000.00
<br />2
<br />CONCRETE SIDEWALK 4 -IN
<br />425
<br />SYS $
<br />55.00
<br />$
<br />23 375.00
<br />3
<br />CONCRETE CURB, REMOVE
<br />675
<br />LFT $
<br />30.00
<br />$
<br />20,250.00
<br />4
<br />CONCRETE CURB MODIFIED
<br />675
<br />LFT $
<br />46.00
<br />$
<br />31.050.00
<br />5
<br />CONCRETE APPROACH REMOVE
<br />75
<br />SYS $
<br />45.00
<br />$
<br />3,375.00
<br />6
<br />PCCP FOR APPROACHES, 6 -IN
<br />75
<br />SYS $
<br />85.00
<br />$
<br />6,375.00
<br />7
<br />TOPSOIL AND SEEDING
<br />375
<br />SYS $
<br />40.00
<br />$
<br />15 000.00
<br />11
<br />TREE. REMOVE 30 IN
<br />1
<br />EA $
<br />1,000.00
<br />$
<br />1,000.00
<br />12
<br />TREE, REMOVE, 48 IN
<br />1
<br />EA $
<br />4,000.00
<br />$
<br />4,000.00
<br />13
<br />STUMP REMOVE
<br />1
<br />EA S
<br />200.00
<br />$
<br />200.00
<br />14
<br />PLANT, DECIDUOUS TREE, SINGLE STEM, 2 -IN
<br />TO 2.5 IN
<br />3
<br />$
<br />EA
<br />1,195.00
<br />$
<br />3,585.00
<br />15
<br />CURB RAMP. REMOVE
<br />15.5
<br />SYS
<br />110.00
<br />$
<br />1,705.00
<br />16
<br />ONE-WAY PERPENDICULAR CURB RAMP
<br />9
<br />SYS $
<br />195.00
<br />$
<br />1.755.00
<br />18
<br />DEPRESSED CORNER CURB RAMP
<br />6.5
<br />SYS $
<br />195.00
<br />$
<br />1,267.50
<br />DIVISION D1 TOTAL
<br />$
<br />129,937.50
<br />
|