Laserfiche WebLink
Mitigation and Construction Plan <br />The temporary supports that we have previously placed are on weak surfaces. Collapse is a great risk <br />as is, but very likely to occur with the weight of snow. The time of year and expected time frame of the <br />project precludes this being completed before winter, so work shall be done in 2 phases: <br />1. demolition and safety securing of the site — as soon as approved and permitted <br />2. rebuild — in Spring 2019 <br />The detail of the demolition is outlined in Jeff Weldy's proposal included separately here. <br />• <br />