OWNER: City of South Bend <br />Project Supervisor: Lochmueller Group, Inc. <br />Myron Cohagan <br />CONTRACTOR: Larson Danielson <br />PROJECT: Howard Park Redevelopment <br />Project No. 117-047-B <br />SUBJECT: Unexpected Construction Changes <br />ISSUE DATE: Feb 1, 2020 <br />This Change Order to the Contract document shall supplement, amend, and shall <br />become a part <br />of, and be incorporated as an Addendum to the Contract. <br />The following is a summary and description of the revisions to the Contract by this <br />Change Order: <br />The following sections of the Contract Documents are revised as a result of the <br />above changes: <br />Howard Park Completion date will be extended an additional 145 days to <br />May 8t" 2020. This will allow for the commissioning of the water feature and <br />completion of other weather related punch list items. <br />1. Cafe Temp Lights 269.97 <br />See Change Request 182 <br />2. UPS for Ice Rink Control 702.15 <br />See Change request 183 <br />3. Skate sharpener Outlet 705.49 <br />See Change Request 184 <br />4. BY Pass Per ASI #39 (Hot Water) 797.70 <br />See Change request 185 <br />5. Relocate Thermostats 822.14 <br />