REGULAR MEETING OCTOBER 8, 2019 297 <br />APPROVE CHANGE ORDER NO. 1 MICHIGAN STREET PAVEMENT REPLACEMENT <br />— PROJECT NO. 118-075 (RWDA TIFF <br />Mr. Gilot advised that Mr. Roger Nawrot, Engineering, has submitted Change Order No. 1 on <br />behalf of Walsh & Kelly, Inc., 24358 SR 23, South Bend, IN 46614, indicating the contract <br />amount be increased by $25,195.60, plus an additional twenty-one (21) days, for a new contract <br />sum, including this Change Order, in the amount of $1,937,594.60 and a new project completion <br />date of November 5, 2019. Upon a motion made by Ms. Maradik, seconded by Ms. Miller and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 9 — HOWARD PARK REDEVELOPMENT — PROJECT <br />NO. 117-047B (PARK BOND/RETIF/REGIONAL CITIES & CUMULATIVE CAPITAL) <br />Mr. Gilot advised that Mr. Roger Nawrot, Engineering, has submitted Change Order No. 9 on <br />behalf of Larson -Danielson Construction Company, Inc., 302 Tyler Street, LaPorte, IN 46350, <br />indicating the contract amount be increased by $128,359 for a new contract sum, including this <br />Change Order, in the amount of $18,345,759.58. Upon a motion made by Ms. Maradik, <br />seconded by Ms. Miller and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 - EAST LONGFELLOW AVE. AND NORTH <br />RIVERSIDE DRIVE TRAFFIC CALMING — PROJECT NO. 118-113 (LRSA CAPITAL) <br />Mr. Gilot advised that Ms. Theresa Harrison, Engineering, has submitted Change Order No. 1 on <br />behalf of Walsh & Kelly, Inc., 24358 State Road 23, South Bend, IN 46614, indicating the <br />contract amount be increased by $3,473.94, plus an additional forty-six (46) days for a new <br />contract sum, including this Change Order, in the amount of $76,323.94 and a new project <br />completion date of July 31, 2019. Upon a motion made by Ms. Maradik, seconded by Ms. Miller <br />and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — WASTEWATER TREATMENT PLANT <br />ELECTRICAL IMPROVEMENTS —PROJECT NO. 117-132 (SEWAGE WORKS CAPITAL) <br />Mr. Gilot advised that Mr. Jacob Klosinski, Utilities, has submitted Change Order No. 1 on <br />behalf of Martell Electric, LLC, 4601 Cleveland Road, South Bend, IN 46628, indicating the <br />contract amount be increased by $84,059 for a new contract sum, including this Change Order, in <br />the amount of $6,416,399. Upon a motion made by Ms. Maradik, seconded by Ms. Miller and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 - LIBERTY TOWER EXTERIOR RENOVATIONS <br />DIVISION B — PROJECT NO. 118-086R (RWDA TIF) <br />Mr. Gilot advised that Mr. Kyle Silveus, Engineering, has submitted Change Order No. 1 on <br />behalf of Mulder Waterproofing and Sealants, Inc., 3420 Ravine Road, Kalamazoo, MI 49026, <br />indicating the contract amount be increased by $11,715 for a new contract sum, including this <br />Change Order, in the amount of $308,665. Upon a motion made by Ms. Maradik, seconded by <br />Ms. Miller and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 4 - LIBERTY TOWER EXTERIOR RENOVATIONS. <br />DIVISION C — PROJECT NO. 118-086R (RWDA TIF) <br />Mr. Gilot advised that Mr. Kyle Silveus, Engineering, has submitted Change Order No. 4 on <br />behalf of Environmental Glass, Inc., 12675 Martin Drive, Redford, MI 48239, indicating the <br />contract amount be increased by $2,975.31 for a new contract sum, including this Change Order, <br />in the amount of $308,781.08. Upon a motion made by Ms. Maradik, seconded by Ms. Miller <br />and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 (FINAL) AND PROJECT COMPLETION AFFIDAVIT <br />- 2019 TREE AND STUMP REMOVAL — PROJECT NO. 119-012 (MVH) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 (Final) on <br />behalf of K&R Tree Service LLC, 1724 S. Grant St., South Bend, IN 46613, indicating the <br />contract amount be decreased by $2,312.00 for a new contract sum, including this Change Order, <br />of $24,743.00. Additionally submitted was the Project Completion Affidavit indicating this new <br />final cost of $24,743.00. Upon a motion made by Ms. Maradik, seconded by Ms. Miller and <br />carried, Change Order No. 1 (Final) and the Project Completion Affidavit were approved. <br />APPROVE PROJECT COMPLETION AFFIDAVIT — CENTURY CENTER EXTERIOR <br />SIGNAGE — PROJECT NO. 118-035B (HOTEL/MOTEL TAX) <br />