Laserfiche WebLink
REGULAR MEETING AUGUST 13, 2019 234 <br />APPROVE CHANGE ORDER NO. 3 — MIAMI STREET BASIN DRAINAGE <br />IMPROVEMENTS — PROJECT NO. 116-082C (SSDA TIFF <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 3 on behalf <br />of HRP Construction, Inc., 5777 Cleveland Rd., South Bend, Indiana 46624, indicating the <br />contract amount be increased by $3,010 for the above project, for a new contract sum, including <br />this Change Order, in the amount of $504,790. Upon a motion made by Ms. Maradik, seconded <br />by Ms. Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — UNITY GARDENS LEARNING CENTER SITE <br />IMPROVEMENTS —PROJECT NO. 117-05OR (RWDA TIFF <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 on behalf <br />of Ritschard Bros., Inc., 1204 W. Sample St., South Bend, Indiana 46619, indicating the contract <br />amount be increased by $4,381.85 for the above project for a new contract sum, including this <br />Change Order, in the amount of $73,541.85. Upon a motion made by Ms. Maradik, seconded by <br />Ms. Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 2 — SOUTH BEND FIRE DEPARTMENT TRAINING <br />CENTER CLASSROOM BUILDING — PROJECT NO 117-127 (FIRE STATION NO 9 <br />CAPITAL) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 2 on behalf <br />of Brown and Brown General Contractors, Inc., 124 S Elkhart St., Wakarusa, IN 46573, <br />indicating the contract amount be increased by $6,140 for the above project, for a new contract <br />sum, including this Change Order, in the amount of $658,228. Upon a motion made by Ms. <br />Maradik, seconded by Ms. Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — THREE TWENTY AT THE CASCADE, GLAZED <br />ASSEMBLIES —PROJECT NO. 118-074A (REDA TIF) <br />Mr. Gilot advised that Mr. Zach Hurst, Engineering, has submitted Change Order No. 1 on <br />behalf of Precision Wall Systems, Inc., 3801 S. Main Street, South Bend, Indiana 46614, <br />indicating the contract amount be increased by $24,632, plus an additional fifty-four (54) days, <br />for the above project, for a new contract sum, including this Change Order, in the amount of <br />$1,472,632 and a new project completion date of October 15, 2019. Upon a motion made by Ms. <br />Maradik, seconded by Ms. Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — ST. JOSEPH STREET IMPROVEMENTS — PROJECT <br />NO. 118-008 (SSDA TIF) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 on behalf <br />of Walsh & Kelly, Inc., 24358 State Road 23, South Bend, Indiana 46614, indicating the contract <br />amount be increased by $26,436.52 and an additional ninety-two (92) days for the above project, <br />for a new contract sum, including this Change Order, in the amount of $449,436.52 and a revised <br />completion date of March 1, 2019. Upon a motion made by Ms. Maradik, seconded by Ms. <br />Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — LAFAYETTE BUILDING DRAIN REPLACEMENT — <br />PROJECT NO. 119-042 (RWDA TIFF <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 on behalf <br />of Niezgodski Plumbing, Inc., 232 North Mayflower Road, South Bend, Indiana 46619, <br />indicating the contract amount be increased by $20,745.60 for the above project for a new <br />contract sum, including this Change Order, in the amount of $57,872.60. Upon a motion made by <br />Ms. Maradik, seconded by Ms. Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 5 — LINCOLNWAY WEST AND CHARLES MARTIN <br />SR. DRIVE IMPROVEMENTS — PROJECT NO 117-072A (RWDA TIF) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 5 (Final) on <br />behalf of Selge Construction Co., Inc., 2833 S. 1 It' Street, Niles, Michigan 49120, indicating the <br />contract amount be decreased by $875 for the above project, for a new contract sum, including <br />this Change Order, of $1,197,648.10. Also submitted was the Project Completion Affidavit <br />indicating this new final cost of $1,197,648.10. Ms. Maradik stated there was a discussion about <br />a punch list of items still needing to be completed and questioned whether the project was ready <br />to be closed out. After discussion with Mr. Kyle Silveus, Engineer, the Board determined to <br />