Laserfiche WebLink
REGULAR MEETING DECEMBER 20, 2018 404 <br />Mr. Gilot advised that Ms. Becca Plantz, Engineering, has submitted Change Order No. 1 on <br />behalf of Peerless Midwest, Inc., 55860 Russell Industrial Parkway, Mishawaka, IN 46545, <br />indicating the contract amount be increased by $13,149 for a new contract sum, including this <br />Change Order, in the amount of $63,140. Ms. Plantz stated this well had a carbon shaft that was <br />deteriorated and had to be replaced. Upon a motion made by Ms. Dorau, seconded by Ms. <br />Fritzberg and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — ANGELA BRIDGE LIGHTING PROJECT — <br />PROJECT NO. 116-111 (COIT) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 on behalf <br />of Martell Electric, LLC, 4601 Cleveland Road, South Bend, IN 46628, indicating the contract <br />amount be increased by $2,974.69 for a new contract sum, including this Change Order, in the <br />amount of $51,996.69. Upon a motion made by Ms. Dorau, seconded by Ms. Fritzberg and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO 7 (FINAL) — DOWNTOWN CROSS STREET <br />IMPROVEMENTS — PROJECT NO 117-041A (LRSA <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 7 (Final) on <br />behalf of Walsh & Kelly, Inc., 24358 SR 23, South Bend, IN 46614, indicating the contract <br />amount be increased by $25,159.95 for a new contract sum, including this Change Order, in the <br />amount of $1,753,886.17. Upon a motion made by Ms. Dorau, seconded by Ms. Fritzberg and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 — 2018 CURB AND SIDEWALK CONSTRUCTION <br />DIVISIONS Al, Bl, C, D1, D2 E G1 AND G2 — PROJECT NO 118 007 (MVH) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 1 on behalf <br />of Rieth-Riley Construction Co., Inc., 25200 State Road 23, South Bend, IN 46614, indicating <br />the contract amount be increased by $87,550.02, plus an additional two -hundred seven (207) <br />days, for a new contract sum, including this Change Order, in the amount of $661,895.99 and a <br />new project completion date of April 30, 2019. Ms. Kara Boyles, City Engineer, stated they were <br />unable to award two (2) divisions at the beginning of the year, but they are now adding in the <br />second division after finding the funding. She confirmed Mr. Gilot's assessment that there was a <br />lag in the funding that caused the time delay. Upon a motion made by Ms. Dorau, seconded by <br />Ms. Fritzberg and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 4 — CHARLES BLACK CENTER RENOVATION — <br />PROJECT NO. 116-073 (PARK BOND) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted a revised Change Order No. 4 <br />on behalf of Gibson -Lewis, LLC, 1001 W 11 th Street, Mishawaka, IN 46544, indicating the <br />contract be increased by $51,823 for a revised new contract sum, including this Change Order, in <br />the amount of $3,973,460. Upon a motion made by Ms. Dorau, seconded by Ms. Fritzberg and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 2 — BERLIN PLACE NO. 2 ELECTRICAL <br />MECHANICAL AND PLUMBING — PROJECT NO 117-048R (RWDA TIF) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 2 on behalf <br />of CBS Services, LLC, 5005 Lincolnway East, Suite A, Mishawaka, IN 46544, indicating the <br />contract completion date be increased by two -hundred (200) days for a new contract completion <br />date of May 31, 2019. Upon a motion made by Ms. Dorau, seconded by Ms. Fritzberg and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO 5 (FINAL) AND PROJECT COMPLETION AFFIDAVIT <br />— 2016 MANHOLE AND SEWER LINING — PROJECT NO. 116-026 UTILITY <br />EXPENSE/CONTRACTUAL SERVICE OTHER) <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 5 (Final) on <br />behalf of Insituform Technologies USA, LLC, 17988 Edison Ave., Chesterfield, MO 63005, <br />indicating the contract amount be decreased by $162,538.70 for a new contract sum, including <br />this Change Order, of $2,837,196.20. Additionally submitted was the Project Completion <br />Affidavit indicating this new final cost of $2,837,196.20. Upon a motion made by Ms. Dorau, <br />seconded by Ms. Fritzberg and carried, Change Order No. 5 (Final) and the Project Completion <br />Affidavit were approved. <br />