REGULAR MEETING NOVEMBER 13 2018 348 <br />amount be increased by $13,077,31 for a new contract sum, including this Change Order, in the <br />amount of $143,257.31. Upon a motion made by Ms. Maradik, seconded by Ms. Dorau and <br />carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. I WASTEWATER TREATMENT PLANT <br />HEADWORKS GATE IMPROVEMENTS - PROJECT NO. 117-026 CUTILITIFS <br />WASTEWATER CAPITAL) <br />Mr. Gilot advised that Mr. Jacob Klosinski, Utilities, has submitted Change Order No. 1 on <br />behalf of HRP Construction, Inc., 5777 Cleveland Road, South Bend, IN 46624, indicating the <br />contract amount be decreased by $351,345.56 plus an additional twenty (20) days, for a new <br />contract sum, including this Change Order, in the amount of $615,154.44 and a new project <br />completion date of November 16, 2018. Upon a motion made by Ms. Maradik, seconded by Ms. <br />Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 1 - ERSKINE CLUBHOUSE RENOVATION - PROJECT <br />NO. 116-108' CGOLF OPERATIONa) <br />Mr. Gilot advised that Mr. Kyle Silveus, Engineering, has submitted Change Order No. I on <br />behalf of .Ziolkowsk:i Construction, Inc., 4050 Ralph Jones Drive, South Bend, IN 46628, to <br />eliminate Intermediate Phase I completion date of November 30, 2018. He noted there is no <br />change in final completion date or contract amount. Upon a motion made by Ms. Maradik, <br />seconded by Ms. Doran and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 2 - ERSKINE CLUBHOUSE RENOVATION -- PROJECT <br />NO. H6-108(GOLF OPERATIONS <br />Mr. Gilot advised that Mr. Kyle Silveus, Engineering, has submitted Change Order No. 2 on <br />behalf of Ciolkowski Construction, Inc., 4050 Ralph Jones Drive, South Bend, IN 46628, <br />indicating the contract amount be increased by $7,899 for a new contract sung, including this <br />Change Order, in the amount of $914,899. Upon a motion made by Ms. Maradik, seconded by <br />Ms. Dorau and carried, the Change Order was approved. <br />APPROVE CHANGE ORDER NO. 2 FINAL AND PROJECT" COMPLETION AFFIDAVIT <br />DOWNTOWN BRIDGE STRIPING - PROJECT NO. 117-12'LRSA/LANE MARKINGS <br />& LRSA/S'.I'REET MAIN°I"FNANCEI <br />Mr. Gilot advised that Mr. Toy Villa, Engineering has submitted Change Order No. 2 (Final) on <br />behalf of The Airmarking Co., Inc., 1544 N. State Road 25, Rochester, IN 46975 indicating the <br />contract amount be decreased by $445.05 for a new contract sum, including this Change Order, <br />of $86,357.15. Additionally submitted was the Project Completion Affidavit indicating this new <br />final cost of $86,357.15. Upon a motion made by Ms. Maradik, seconded by Ms. Dorau and <br />carried, Change Order No. 2 (Final) and the Project Completion Affidavit were approved. <br />APPROVE PROJECT CC)11PLETTON AFFIDAVIT MISIIAWAKA AVENUE ROTO <br />ROOT"ER JE'"1'TER REMOVAL - PI.OJECT NO. l 18 069R :aE'WER CAPITAL <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted the Project Completion <br />Affidavit on behalf of Selge Construction Co., I2833 S. 11 « Street, Niles, MI 49120, for the <br />above referenced project, indicating a final cast of $72,307. Upon a motion made by Ms. <br />Maradik, seconded by Ms. Doran and carried, the Project Completion Affidavit was approved. <br />APPROVE PROJECT COMPLETION AFF"1DAV1T - FLIR TRAFFIC CAMERA <br />REPLACEMENTS PROJECT NO. 118-006 `LRSA <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted the Project Completion <br />Affidavit on behalf of Pemberton Davis Electric, I916 E. McKinley Ave., Mishawaka, IN <br />46545 for the above referenced project, indicating a final cost of $123,866.10. Upon a motion <br />made by Ms. Maradik, seconded by Ms. Dorau and carried, the Project Completion Affidavit <br />was approved. <br />APPROVE PROJECT COMPLETION AFl"CIJAVIT - FI,1R TRAFFIC CAMERAS,. <br />DIVISIONS A BAND C - IaROJECT N0. 117-122 LRSA <br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted the Project Completion <br />Affidavit on behalf of Pemberton Davis Electric, I9l6 E. McKinley Ave., Mishawaka, IN <br />46545 for the above referenced project, indicating a final cost of $l l 1,848. Upon a motion made <br />by Ms. Maradik, seconded by Ms. Dorau and carried, the Project Completion Affidavit was <br />approved. <br />