Laserfiche WebLink
May 4, 2011 = a, <br />City of South Bend <br />IL Proposal for Professional Services <br />LaSalle Square, Phase One - Roadway and Utility Design ABONMARCHE <br />Bonds Avenue Extension and New City Street Adjacent to Library Page S of S <br />APPENDIX C <br />ANTICIPATED PROJECT SCHEDULE <br />From past meetings, Sterling Development has indicated starting construction the first of <br />September. This would require a cleared restaurant property and the sanitary sewer main to <br />be relocated. Below are project milestones in order to meet the requested time frame. <br />Project Milestones Estimated Completion Date <br />Demolition of Restaurant (cleared site) <br />Relocated Sanitary Sewer Main <br />Relocated Water Main & Hydrants <br />(for wood framing to commence) <br />Mid August <br />Mid August <br />October (estimated) <br />F: \Proposals \P thru T \S \South Bend CityVaSalle Square \Phase 1 - Road Design \Appendices 05 -04 -1 l .doc <br />IL <br />Engineers <br />Landscape Architects Planners Surveyors <br />