Laserfiche WebLink
City of South Bend Project No. 114-062B <br />Change Order No. 6 - 2/23/17 <br />OWNER: City of South Bend <br />ENGINEER: City of South Bend Engineering <br />Kara M. Boyles, P.E. <br />Professional Engineer No. 10809510 <br />CONTRACTOR: Walsh & Kelly, Inc. <br />PROJECT: East Bank Sewer Separation - Phase 5 (Division B) <br />Project No. 114-062B <br />SUBJECT: Change Order Explanation <br />ISSUE DATE: February 23, 2017 <br />This Change Order to the Contract document shall supplement, amend, and shall become a <br />part of, and be incorporated as an Addendum to the Contract. <br />The following is a summary and description of the revisions to the Contract by this Change <br />Order: <br />Item <br />QtV Unit <br />1. Line Item Reductions <br />(See attached) <br />2. Add Soil Removal <br />8,300 Tons <br />3. Add Borrow <br />2,561 CYD <br />Price Days Total <br />($328,098.46) <br />$40 0 $332,000.00 <br />$18 0 $46,098.00 <br />Net Change Order amount $49,999.54 <br />[Funding approved from account number: 429.1050.460.42.03 (Project 15J016)] <br />1) Line Item Reductions are being used to reallocate funds to pay for unsuitable soil removals. <br />Originally planned streetscape work along St. Louis Blvd, Jefferson Blvd, and the northernmost <br />portion of St. Peter St are being eliminated so the money can be used for soil disposal costs. <br />Please refer to the attached line item/quantity breakdown for items being eliminated from the <br />project. <br />2) The Soil Removal line item is needed for the disposal of unsuitable soils and the associated <br />tipping fees. The unsuitable soils are located at Northside Blvd through 215 feet north along <br />what will become St. Peter St. Soil to be removed is about 75 feet wide and 12 feet deep. <br />3) The Borrow line item is needed so structural backfill can be hauled in to replace the removed <br />unsuitable soils for use within the roadway. <br />