1. REVISE to indicate that removal of all sidewalk, including curb ramps, shall be included
<br />in the "Pavement, Concrete, Remove" line item.
<br />B. Items B, No. 5
<br />1. DELETE sentence "Removal and replacement of existing pavement shall not be paid for
<br />separately, but included in the cost of the removal items."
<br />2.04 SPECIAL PROVISIONS, Page 19, Section XXXDf, Structure Remove, Section B, Item 3
<br />1. REVISE to read "Structure removal excavations shall he backfilled with INDOT B-
<br />Borrow granular backfill, to be paid for under the Morrow line item.
<br />2.05 SPECIAL PROVISIONS, Page 20, Section XL, Pipe Remove, Section B, Item 4.a
<br />1. REVISE to indicate that insertion valve to be installed as noted in the plans shall be 6-inch.
<br />2.06 SPECIAL PROVISIONS, Page 20, Section XLI, Existing Foundation, Debris Removal &
<br />Replacement, Section B, Item 3
<br />1. REVISE to read "Excavations for foundations and/or debris removal shall be backfilled
<br />with INDOT B-Barrow granular backfill, to be paid for under the B-Borrow line item.
<br />2.07 SPECIAL PROVISIONS, Page 30, Section LVIII, Storm Sewer Pipe, Section B, Item 6
<br />1. REVISE to read "Pipe installation shall be backfilled as shown on the plans or as directed.
<br />Prior to and during placement of bedding material and backfill, all standing water shall be
<br />removed from the trench. Storm sewer trench backfill shall be structural backfill to the top
<br />of the sewer pipe and B-Borrow backfill to the top of the trench. Backfill shall be paid with
<br />Structural Backfill and B-Borrow line items, respectively."
<br />2.08 SPECIAL PROVISIONS, Page 31, Section LIX, Sanitary Sewer Pipe, Section B, Item 6
<br />1. REVISE to read "Installation of the sanitary sewer pipe shall be in accordance with the
<br />pipe manufacturer's recommendations, ASTM D2321, the City of South Bend
<br />requirements and IDEM's requirements. Sanitary sewer trench backfill shall be structural
<br />backfill to the top of the sewer pipe and B-Borrow backfill to the top of the trench. Backfill
<br />shall be paid with Structural Backfill and B-Borrow line items, respectively."
<br />2.09 SPECIAL PROVISIONS, Bid/Proposal Form:
<br />1. REPLACE: Bid/Proposal Form, with attached Bid/Proposal Form, Item 9. Tree, Remove,
<br />Item 9, quantity was revised from 31 to 5.
<br />2. REPLACE: Bid/Proposal Form, with attached Bid/Proposal Form, Item 22. Structural
<br />Backfill, Type 2, quantity was revised from 6,400 CYS to 550 CYS.
<br />3. ADD: Bid/Proposal Form, Item 23, B-Borrow, 6,000 CYS.
<br />PART 3 — CONSTRUCTION DOCUMENTS
<br />3.01 Plan Sheet X-2209-02 — Demolition Note 5 —Temporary Security Fence
<br />1. ADD: Refer to the attached Addendum #1 plan sheet for layout of proposed temporary
<br />security fence.
<br />3.02 Plan Sheet X-2209-02--Site Demolition
<br />Berlin Place Site Development (116-089) Addendum # I
<br />November 14, 20I6 page 12