Laserfiche WebLink
Change Order No. 27 <br />One- Way to Two -Way Street Conversion <br />Division B <br />Project No. 116-001 <br />OWNER: City of South Bend <br />ENGINEER: American Structurepoint, Inc. <br />Patrick K. Wooden, P.E. <br />Professional Engineer No. 10504741 <br />CONTRACTOR: Rieth-Riley Construction <br />PROJECT: South Bend One -Way to Two -Way Conversion Division B <br />Project No. 116-001 <br />SUBJECT: Light Pole Foundations <br />ISSUE DATE: October 3, 2016 <br />This Change Order to the Contract document shall supplement, amend, and shall become a <br />part of, and be incorporated as an Addendum to the Contract. <br />The following is a summary and description of the revisions to the Contract by this Change <br />Order: <br />Several light pole foundations along the west side of Main Street between Western <br />Avenue and LaSalle Avenue have been identified as being in conflict with an <br />existing AEP duct bank. A spread footer design has been developed to remedy <br />such conflicts. This footer is to be utilized on an as needed basis in lieu of the <br />drilled shaft specified in the original construction documents. The details of this <br />spread footer are provided in Division B Part 1 of 3 Revision 16. <br />The following sections of the Contract Documents are revised as a result of the above changes: <br />1. Bid/Proposal Form: <br />Division B: <br />New EWA Line Item No.471: LIGHT POLE FOUNDATION SPREAD FOOTER, 30 EA <br />@ $ 1,928.39/EA for a total addition of $57,851.70. <br />Subtract 30 EACH to Line Item No. 296 LIGHT STANDARD FOUNDATION, 2FT <br />DIAMETER X 6FT, -30 EACH @ $560.00/EACH for a total deduction of (-$16,800.00) <br />Sheet 1 of 3 <br />