Laserfiche WebLink
Change Order No.2 <br />Century Center Electrical Distribution Upgrades <br />Project No. 116-007 <br />OWNER: City of South Bend <br />ENGINEER: M/E Design Services <br />CONTRACTOR: Days Electrical <br />PROJECT: Century Center Electrical Distribution Upgrades <br />SUBJECT: Clarifications and Revisions to Contract Documents <br />ISSUE DATE: September 16, 2016 <br />This Change Order to the Contract document shall supplement, amend, and shall become a part of, <br />and be incorporated as an Addendum to the Contract. <br />The following is a summary and description of the revisions to the Contract by this Change Order: <br />Replaced the damaged fused switch feeding AHU-3 and AHU-4. During repair of fused <br />switch located in the main switchgear for an issue that was found during thermal scan <br />of equipment is was discovered that the switch was damaged beyond repair. Parts for <br />the existing switchgear are no longer available so the existing fused switch was <br />replaced with a new remote mounted 200 amp fused safety switch. This was an <br />emergency repair that was required to keep the AHU's operational at the facility. <br />SHEET 1 OF 2 <br />