INTER -OFFICE MEMORANDUM <br />DEPARTMENT OF PUBLIC WORKS <br />DIVISION OF ENGINEERING <br />TO: Linda M. Martin, Clerk <br />Board of Public Works <br />FROM: Richard Estes, Engineer I <br />SUBJECT: Change Order #2 for Century Center Electrical Distribution Upgrades <br />Project No. 116-007 <br />DATE: September 16, 2016 <br />Herewith is an explanation for the Change Order being submitted. <br />The reason(s) for the Change Order request are as follows: <br />Replaced the damaged fused switch feeding AHU-3 and AHU-4. During repair of fused <br />switch located in the main switchgear for an issue that was found during thermal scan <br />of equipment is was discovered that the switch was damaged beyond repair. Parts for <br />the existing switchgear are no longer available so the existing fused switch was <br />replaced with a new remote mounted 200 amp fused safety switch. <br />Items 1 is an emergency repair that was required when it was found that the existing fused switch had <br />failed. The cost for the work will be $1,376.00. This brings the total increase to 18.15% for the overall <br />project cost. This includes previously approved changes of $12,432.08 in change order #1. <br />Please call me with your questions (5896). <br />