<br />REGULAR MEETING MAY 28. 1996
<br />APPROVE CONSTRUCTION CONTRACTS - 1996 PUBLIC WORK PARTNERSHIP
<br />PROGRAM - ZONES 11D 2 9 10 11A AND 11B - PROJECT NO. 96-09
<br />Mr. Leszczynski advised that in accordance with the bid awarded on May 6, 1996, to Niles Concrete
<br />Sawing and Construction, 2580 East Detroit Road, Niles Michigan, for the above referred to project,
<br />Contracts for each Zone were being submitted for Board approval, as follows:
<br />Zone 11 D
<br />$63,911.00
<br />Zone 2
<br />$59,312.00
<br />Zone 9
<br />$52,279.00
<br />Zone 10
<br />$55,063.00
<br />Zone 11A & 11B
<br />$66,504.50
<br />Upon a motion made by Mr. Caldwell, seconded by Mr. Leszczynski and carried, the Contracts were
<br />approved and the appropriate Certificates of Insurance, Performance Bonds and Labor and Materials
<br />Payment Bonds as submitted were filed.
<br />APPROVE CONSTRUCTION CONTRACTS - 1996 _ PUBLIC WORK PARTNERSHIP
<br />PROGRAM - ZONES 1, 3, 4. 5, and 11C - PROJECT NO. 96-09
<br />Mr. Leszczynski advised that in accordance with the bid awarded on May 6, 1996, to Rieth Riley
<br />Construction, 25700 State Road 23, South Bend, Indiana, for the above referred to project, Contracts
<br />for each Zone were being submitted for Board approval, as follows:
<br />Zone 1
<br />$55,552.00
<br />Zone 3
<br />$63,435.25
<br />Zone 4
<br />$61,547.00
<br />Zone 5
<br />$59,765.00
<br />Zone 11C
<br />$71,549.45
<br />Upon a motion made by Mr. Leszczynski, seconded by Mr. Caldwell and carried, the Contracts were
<br />approved and the appropriate Certificates of Insurance, Performance Bonds and Labor and Materials
<br />Payment Bonds as submitted were filed.
<br />APPROVE CONSTRUCTION CONTRACT - SOUTHEAST PARTNERSHIP CENTER -
<br />SIDEWALK. CURB AN APPROACH REPAIRS - PROJECT NO. 95-1 lA
<br />Mr. Leszczynski advised that in accordance with the bid awarded on May 13, 1996, to Walsh &
<br />Kelly, 24358 State Road 23, South Bend, Indiana, in the amount of $21,758.30 for the above referred
<br />to project, a Contract in said amount was being submitted for Board approval. Upon a motion made
<br />by Mr. Caldwell, seconded by Mr. Leszczynski and carried, the Contract was approved and the
<br />appropriate Certificate of Insurance, Performance Bond and Labor and Materials Payment Bond as
<br />submitted were filed.
<br />APPROVE COMMUNITY DEVELOPMENT ADDENDA
<br />The following Community Development Addenda were presented to the Board for approval:
<br />South Bend Heritage Addendum I Reduces budget to $55,000
<br />Housing Development Addendum IV Extends contract to September 30, 1996
<br />Upon a motion made by Mr. Caldwell, seconded by Mrs. Manier and carried, the above referred to
<br />Addenda were approved and executed.
<br />APPROVAL OF UTILITY AGREEMENT - NORTHSIDE WALKWAYBIKEWAY - PROJECT
<br />NO. 95-22
<br />Mr. Leszczynski stated that the Board is in receipt of an Agreement between the City of South Bend
<br />and Northern Indiana Public Service Company, for utilities to be retained, installed, adjusted or
<br />relocated along or under the highway within the right-of-way limits in conjunction with the above
<br />referred to project. Therefore, upon a motion made by Mr. Caldwell, seconded by Mrs. Manier and
<br />carried, the Agreement was approved and executed.