REGULAR MEETING APRIL 7, 1997
<br />Zone Number Amount
<br />Zone 6, 7, 8 $54,055.00
<br />RIETH RILEY CONSTRUCTION CO., INC.
<br />Post Office Box 1775
<br />South Bend, Indiana 46634
<br />Zone Number
<br />Amount
<br />Zone I IC
<br />$53,594.50
<br />Zone IID
<br />$57,578.00
<br />L.E. BARBER INC.
<br />1200 East Napier Avenue
<br />Benton Harbor, Michigan
<br />Zone Number
<br />Amount
<br />Zone 1
<br />$50,358.55
<br />Zone 2
<br />$57,463.75
<br />Zone 3
<br />$50,753.50
<br />Zone 4
<br />$51,941.25
<br />Zone 5
<br />$58,260.00
<br />Zone 9
<br />$47,350.00
<br />Zone 10, 11A, 11B
<br />$57,092.50
<br />Therefore, Mr. Caldwell made a motion that the recommendation be accepted and the bids be
<br />awarded as outlined above. Ms. Roemer seconded the motion which carried.
<br />AWARD BID - ONE (1) 10' CARGO VAN
<br />Mr. Matt Chlebowski, Director, Division of Engineering, advised the Board that on March 17, 1997,
<br />bids were received and opened for the above referred to van. After reviewing those bids, Mr.
<br />Chlebowski recommends that the Board award the bid to Rudd Equipment, 2655 Kentucky Avenue,
<br />Indianapolis, Indiana in the amount of $78,873.00. Therefore, Mr. Littrell made a motion that the
<br />recommendation be accepted and the bid be awarded as outlined above. Ms. Roemer seconded the
<br />motion which carried.
<br />APPROVE CHANGE ORDER - SAMPLE-EWING SITE CLEARANCE - PHASE III - PROJECT
<br />NO. 96-88
<br />Mr. Caldwell advised that Mr. Toy Villa, Public Construction Manager, has submitted Change Order
<br />No. 2 on behalf of Warner and Sons, 29099 U.S. Highway 33, Elkhart, Indiana indicating that the
<br />Contract amount be increased $2,500.00 for a new Contract sum including this Change Order in the
<br />amount of $65,535.00. Upon a motion made by Ms. Roemer, seconded by Mr. Littrell and carried,
<br />the Change Order was approved.
<br />APPROVE PROJECT COMPLETION AFFIDAVIT - NEW IRRIGATION SYSTEM - ELBEL
<br />GOLF COURSE. STUDEBAKER GOLF COURSE AND ERSKINE GOLF COURSE - PROJECT
<br />NO. 95-16
<br />Mr. Caldwell advised that Mr. Toy Villa, Public Construction Manager, has submitted the Project
<br />Completion Affidavit, on behalf of Wissco Irrigation, Inc., 1820 South Bend Avenue, South Bend,
<br />Indiana, for the above referred to project, indicating a final cost of $651,780.61. Upon a motion
<br />made by Mr. Caldwell, seconded by Mr. Littrell and carried, the Project Completion Affidavit was
<br />approved.
<br />17