REGULAR MEETING NOVEMBER 22, 1999
<br />APPROVE CHANGE ORDER - PINE ROAD SANITARY SEWER - PROJECT NO. 99-64
<br />Mr. Caldwell advised that Mr. Carl Littrell, P.E., Division of Engineering, submitted Change Order
<br />No. 1 , on behalf of Ken Herceg & Associates, indicating that the length of the contract be extended
<br />by 46 calendar days for substantial completion of sewer work. The new contract completion date,
<br />as listed on the change order is December 31, 1999. Upon a motion made by Ms. Roemer, seconded
<br />by Mr. Powell, and carried, the change order was approved. Funding source for this project is
<br />Sewage Works.
<br />APPROVE CHANGE ORDER NO.3-15.10-1 FOR LEIGHTON PLAZA PHASE III - PARKING
<br />GARAGE STRUCTURE - PROJECT NO. 97-57-4
<br />Mr. Caldwell advised that Mr. Carl Littrell, P.E., Division of Engineering, submitted Change Order
<br />No. 3-15.10-1, Plumbing System, on behalf of Apex Mechanical Contractor, Inc., for moving stored
<br />materials in the underground parking structure, with an increase in the contract amount by $476.00
<br />and a new contract sum of $429,524.00. Upon a motion made by Mr. Powell, seconded by Ms.
<br />Roemer and carried, the change order was approved. The funding source is Leighton Plaza Bonds.
<br />TABLED CHANGE ORDER NO. 3-15.10-2 FOR LEIGHTON PLAZA PHASE III - PARKING
<br />GARAGE STRUCTURE - PROJECT NO. 97-57-4
<br />Mr. Caldwell advised that Mr. Carl Littrell, P.E., Division of Engineering, submitted Change Order
<br />No. 3-15.10.2 indicating that the contract amount be increased by $27,050.14 for a new contract sum
<br />of $455, 574.14. Mr. Powell noted that the dollar amounts between the two change orders, 3-15.10-1
<br />and 3-15.10-2, do not add up. Mr. Littrell said that there is a change order, not yet submitted, that
<br />would make these totals add up. Therefore, upon a motion made by Mr. Caldwell, seconded by Mr.
<br />Powell and carried, the change order was tabled until the not yet received order is received.
<br />Funding source for this project is Leighton Plaza Bonds.
<br />APPROVE CHANGE ORDER NO. 3-15.30 FOR LEIGHTON PLAZA PHASE III - PARKING
<br />GARAGE STRUCTURE - PROJECT NO. 97-57-4
<br />Mr. Caldwell advised that Mr. Carl Littrell, P.E., Division of Engineering, submitted Change Order
<br />No. 3-15.30 - HVAC, on behalf of Apex Mechanical Contractor, Inc., for additional HVAC work
<br />improvements, with an increase in the contract amount by $5,032.00 and a new contract sum of
<br />$92,032.00. Upon a motion made by Mr. Powell, seconded by Mr. Caldwell and carried, the change
<br />order was approved. The funding source is Leighton Plaza Bonds
<br />APPROVE FINAL CHANGE ORDER AND PROJECT COMPLETION AFFIDAVIT -
<br />LONGFELLOW AND TWYCKENHAM TRAFFIC CALMINGMEASURES - PROJECT NO.99-
<br />65
<br />Mr. Caldwell advised that Mr. Carl Littrell, P.E., Division of Engineering, submitted the Final
<br />Change Order on behalf of L.L. Geans Construction Co., indicating that the contract amount be
<br />increased by $5,137.20 for a new contract sum of $37,708.20. Also submitted was the Project
<br />Completion Affidavit indicating this new final cost. Upon a motion made by Mr. Powell, seconded
<br />by Ms. Roemer and carried, the Final Change Order and Project Completion Affidavit were
<br />approved, with the appropriate three-year Maintenance Bond. Funding source for this project is the
<br />Local Roads and Streets Account.
<br />RECOMMENDATION - REQUEST TO PURCHASE CITY -OWNED PROPERTY -
<br />SOUTHEAST CORNER OF ARTHUR AND SORIN STREETS
<br />Mr. Caldwell stated that the Board is in receipt of a request for recommendations to purchase City -
<br />owned property, key no. 18-5078-2732, located at the southeast corner of Arthur and Sorin Streets.
<br />All recommendations received (Division of Engineering, Department of Code Enforcement,
<br />Department of Economic Development, Attorney's Office and Department of Public Parks) were
<br />favorable. Therefore, Mr. Powell made motion that the recommendation be approved. Ms. Roemer
<br />seconded the motion, which carried.