HomeMy WebLinkAboutAward Quote - SBPD Explosive Enclosure Proj No 124-031A - Premium Concrete Services
October 13, 2026
Rob Becker
Premium Concrete Services
712 Richmond St.
Elkhart, IN 46516
austin@premiumservices.group
RE: Quotation Award – SBPD Explosive Enclosure – Project No. 124-031A
Dear Rob:
At its October 13, 2026 meeting, the Board of Public Works awarded the above
referenced quotation to you in the amount of $152,906.
Please forward the following documents in one submittal by October27, 2026 to
my attention for Board of Public Works approval at hhorvath@southbendin.gov :
1) One (1) signed original of the Contract (enclosed); and
2) Certificate of Insurance naming the City of South Bend as an additional insured.
Sincerely,
/s/Hillary Horvath
Hillary Horvath, Clerk
October 13, 2026
Jason Yoder
R. Yoder Construction, Inc.
27453 County Road 150, Po Box 69
Nappanee, IN 46550
brad@ryoderconstruction.com
RE: Quotation Award – SBPD Explosive Enclosure – Project No. 124-031A
Dear Jason:
At its October 13, 2026 meeting, the Board of Public Works awarded the above
referenced quotation to Premium Concrete Services in the amount of $152,906.
We thank you for quoting and hope you will quote with us again in the future.
Sincerely,
/s/Hillary Horvath
Hillary Horvath, Clerk
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 13th Day of October, 2026, by and between
Premium Concrete Services, (the “Contractor”), and the Board of Public Works (the
"Board”).
The Contractor covenants and agrees to make the following improvement, as fully set out
in the Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid
Proposals, all of which are set forth as a part of this Contract, for:
PROJECT NO. 124-031A
DESCRIPTION: SBPD EXPLOSIVE ENCLOSURE
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $152,906
FUNDING: PR-00049734
The unit prices for this improvement were those prices as received and accepted by the
Board on the 13th Day of October, 2026.
The Contractor further agrees to notify the assigned Engineer when this improvement is
completed. This notification shall be in the form of a Project Completion Affidavit, signed
by the Contractor. Upon final acceptance of the improvement by the Engineer, the
Contractor’s final estimate will be presented to the Board for final Payment with one (1)
copy of the Project Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that
he/she/it has the authority to bind the named person or entity to this Agreement.
BOARD OF PUBLIC WORKS PREMIUM CONCRETE SERVICES
President Member Printed Name
Member Member Signature
Member Attest: Clerk
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk
Board of Public Works
FROM: Zak Tebell
Project Engineer, Division of Engineering
SUBJECT: Award: 124-031 SBPD Explosive Enclosure
DATE: 9/29/2026
On September 22nd 2026, the Board of Public Works opened and read quotes for the
above project. Two quotes were received.
Contractor Base Quote
C&E Excavation No Quote Provided Majority Builders No Quote Provided Gibson-Lewis, LLC No Quote Provided
Ritschard Bros., Inc No Quote Provided
R. Yoder Construction, Inc $180,630.00
Premium Concrete Services $152,906.00
Engineering recommends award of Base Quote to the lowest and
responsive Quoter, Premium Concrete Services in the amount of
$152,906.00. Sufficient funds have been approved by the police department
for this project. Premium Concrete Services indicated they intend to meet
stipulated MWBE goals for this project.
Please Respond with any questions (EXT. 9358)
Bid TABULATION
SBPD Explosive Enclosure
Project No: 124-031A
For Quotes Due: September 22nd 2026
BASE QUOTE
Item No. Description Quantity Unit Unit Price Item Total Unit Price Item Total
1 Construction Engineering 1 LS 18,000.00$ 18,000.00$ 3,500.00$ 3,500.00$
2 Mobilization /
Demobilization 1 LS 9,000.00$ 9,000.00$ 7,000.00$ 7,000.00$
3 Fence, Remove 150 LF 18.00$ 2,700.00$ 12.50$ 1,875.00$
4
Building ( +/- 720 SF
Bunker) Remove, Full
Depth
1 LS 20,000.00$ 20,000.00$ 6,400.00$ 6,400.00$
5 Clear and grub 1 LS 5,000.00$ 5,000.00$ 6,700.00$ 6,700.00$
6 Tree, Remove
(Undistributed)1 EA 1,500.00$ 1,500.00$ 2,700.00$ 2,700.00$
7 Electric Service
Disconnect (Temporary) 1 EA 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$
8 Earthwork 2500 CY 9.00$ 22,500.00$ 20.00$ 50,000.00$
9 Geotextile Fabric 2880 SF 3.00$ 8,640.00$ 0.75$ 2,160.00$
10 PCCP, 6 IN Reinforced 58 SY 240.00$ 13,920.00$ 230.00$ 13,340.00$
11 No. 2 Crushed Stone
Subbase 125 TON 108.00$ 13,500.00$ 60.00$ 7,500.00$
12 No. 53 Crushed Stone
Base 56 TON 125.00$ 7,000.00$ 61.00$ 3,416.00$
13
No. 73 Crushed
Limestone, Drive
Extension Material
71 TON 125.00$ 8,875.00$ 60.00$ 4,260.00$
14
No. 73 Crushed
Limestone, Entry Drive
Restoration
(Undistributed)
1 TON 220.00$ 220.00$ 250.00$ 250.00$
15 Magazine (Explosives
Bunker) Install 1 EA 10,000.00$ 10,000.00$ 6,000.00$ 6,000.00$
16 Electric Service
Reconnect 1 EA 7,000.00$ 7,000.00$ 7,500.00$ 7,500.00$
17 Fence, Chain Link
w/Barbwire, 8'140 LF 100.00$ 14,000.00$ 107.00$ 14,980.00$
18 Silt Fence 550 LF 8.50$ 4,675.00$ 5.50$ 3,025.00$
19 Seeding, Hydromulch
and 2 IN Topsoil 11000 Sf 1.10$ 12,100.00$ 0.80$ 8,800.00$
BASE QUOTE TOTAL 180,630.00$ 152,906.00$
Non-Collusion Affadavit
I hereby certify that the above truly and accurately represents Quotes received for this project on September 22nd 2026
Zak Tebell, Project Engineer
Premium Concrete Services
Y
R Yoder Construction, Inc
Y
Page 1 of 1
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date: 9/29/2026
Name: Zak Tebell Department of Public Works – Engineering Division
BPW Date: 10/13/2026 Phone Extension: 9358
Required Prior to Submittal to Board
BPW Attorney X Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 1 Traffic Control Resolution
Other: Ratify Emergency
Contract Ease./Encroach
Required Information
Company or Vendor Name Premium Concrete Services
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name SBPD Explosive Enclosure
Project Number 124-031A
Funding Source PR-00049734 Account No. 101-08-080-080-443001--PROJ00000783
Amount
Terms of Contract Award of Quote for the SBPD Explosive Enclosure Project
Special Contract Provisions N/A
Purpose/Description To replace failing explosive enclosure with a new pre-built ATF approved storage enclosure.
For Change Orders Only
Amount of Increase Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date:
$152,906.00