Redevelopment Commission Agenda Item
DATE: 10/5/2026
FROM: Joseph Molnar,
Deputy Director
Department of Community Investment
SUBJECT: Lafayette Building Update
Funding Source* (circle) River West; River East; South Side; Douglas Road; West Washington; RDC General; Riv. East Res.
*Funds are subject to the City Controller's determination of availability; if funds are unavailable, as solely determined by the City Controller,
then the authorization of the expenditure of such funds shall be void and of no effect.
PURPOSE OF REQUEST: Update regarding the Lafayette Building and consideration of next steps should
redevelopment efforts not result in a viable project
SPECIFICS: Below are multiple updates to the RDC regarding the Lafayette Building.
BUILDING CONDITION
On June 8, 2026, a catastrophic fire occurred at the Lafayette Building in downtown South Bend. Prior to
the fire, the RDC and a private developer had entered into a purchase agreement and development
agreement for the property. In late 2024 and early 2025, engineers conducted a detailed assessment of
the Lafayette Building's structure as part of the previous development agreement. By opening walls and
floors, they determined how the building's load-bearing elements were constructed and connected. The
investigation found that key structural components were either inadequate under current building codes,
had been removed during past renovations, or were damaged in the 1940 fire and never properly
replaced.
As a result, the project would have required rebuilding much of the building floor by floor. This would
have necessarily included strengthening the foundation, reconstructing the ground floor, and then
rebuilding each upper floor through the fifth floor. Because of these extensive structural needs, the
project cost estimate increased from approximately $8-10 million to $12-15 million,. The developer
ultimately elected not to proceed with the project, the purchase of the property did not close, and the
development agreement was terminated.
The fire this past June consumed the majority of the roof structure, causing the skylight to collapse to
the ground floor. The roof helps brace the exterior masonry walls, which otherwise lack adequate
support. As a result, parts of the fifth-floor masonry are at risk of collapsing. The fire, along with the
approximately one million gallons of water used to extinguish it, caused additional damage to the fifth-
______________ ___________Pres/V-Pres
ATTEST: __________ _______ _
Date: _____________ _______
APPROVED Not Approved
SOUTH BEND REDEVELOPMENT COMMISSION
October 8, 2026
✓
South Bend
Redevelopment Commission
215 S. Dr. Martin Luther King, Jr. Blvd., Room 301, South Bend, Indiana
floor masonry and exposed lower-floor wood structural members to moisture. Winter freeze-thaw
cycles are expected to accelerate the deterioration of the masonry and further weaken the building.
The effects of the fire significantly complicate any effort to rehabilitate the building in advance of new
occupancy. A third-party engineering consultant estimates the cost of a ‘bare bones’ rehabilitation to be
approximately $11M. Beyond that, the building would still need mechanical, electrical, and plumbing
systems, fire protection, an elevator, architectural buildout, and interior finishing which would then likely
drive the total rehabilitation cost over $20M.
INSURANCE
The cause of the June 8, 2026 fire remains under investigation by the State Fire Marshal. Nevertheless,
the Lafayette Building was covered under a property insurance policy maintained by the City at the time
of the fire, and City staff immediately filed an insurance claim following the loss. The insurer investigated
the claim, including the condition, maintenance, and security of the building prior to the fire, and
ultimately determined that coverage applied and issued a total payment of $3,596,650 to the City. Those
proceeds have been deposited into the Redevelopment Commission’s general fund as the building’s
owner.
REDEVELOPMENT EFFORTS & NEXT STEPS
Staff will continue to actively pursue redevelopment opportunities for the Lafayette Building and remain
engaged in discussions with potential local development partners regarding the property's future.
However, given the building's deteriorating condition, the documented structural concerns, and the
increased risk of further damage during the upcoming winter months, staff is requesting authority to
proceed with demolition if a feasible redevelopment plan cannot be secured within an appropriate
timeframe. This authority would allow the City to respond promptly should redevelopment efforts prove
unsuccessful, while also protecting public safety, limiting additional deterioration, and avoiding costs
associated with continued stabilization and emergency maintenance of the structure.
Staff would use funds already appropriated by the RDC for the property and approved in Resolution No.
3673. If those funds were insufficient, staff requests authority to utilize funds in the RDC General Fund,
including insurance proceeds received in connection with the fire, for demolition and related costs.
In the event staff determines that demolition is warranted, RDC staff will provide timely notice to the
Commission and ensure that Commissioners are kept informed of the status of redevelopment efforts,
the basis for the demolition decision, and the anticipated next steps. If staff identifies a viable
redevelopment opportunity, any proposed acquisition, development, or related agreements will be
presented to the Commission for approval.
Staff requests authority to proceed with demolition of the Lafayette Building if ongoing redevelopment
efforts do not result in a viable redevelopment opportunity and to utilize insurance proceeds received in
connection with the fire, if necessary, to fund demolition and related costs.