RE: Change Order No. 2 – Demolition of 747-749 Harrison Avenue - Project No. 124-
062
Dear Donald:
At its September 22, 2026 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $17,865, bringing the revised contract amount
to $552,788.
Enclosed is a copy of the Change Order for your records.
Sincerely,
/s/Hillary Horvath
Hillary Horvath, Clerk
Page 1 of 1
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk Board of Public Works
FROM: Zach Hurst, PE, Sr. Project Engineer
SUBJECT: Change Order No. 2 - Project No. 124-062
Demolition of 747/749 Harrison Avenue
DATE: 09/15/2026
Change Order No. 2 for the subject project consists of two added charges. The first charge is for unforeseen asbestos abatement in the school portion of the building, opposite from the sanctuary. Asbestos pipe was present in a crawlspace that was previously flooded and inaccessible for inspection. The added cost for this unforeseen work is $12,456.
The second charge is for unforeseen concrete removal and backfill at the rear of the church. A vault was present underneath the public alley and needed to be removed back to the property line and then properly backfilled. The added price for this unforeseen work is $5,409.
The sum total of Change Order 2 is $17,865.
All added charges to this project, consisting of Change Orders 1 and 2, are unforeseen charges.
DATE: PROJECT NO:
PROJECT NAME:
CONTRACT DATE: CHANGE ORDER NO.
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS PROJECT CHANGE ORDER
09/15/2026
124-062
Demolition of 747-749 Harrison Avenue
03/10/2026
2
SUBJECT OF CHANGE ORDER: CO #2 includes unforeseen asbestos abatement and concrete
removal. See attached memo.
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this cha order
New completion date/time
Contractor Signature
Donald Ritschard, Jr., Vice �resident
Printed Name and Title
Ritschard Bros,, Inc.
Company name
1204 W. Sample Street
$ 443,486
$ 91,437
$ 534,923
[8J Increased D Decreased $ 17,865
$ 552,788
4.0
24.6
05/01/2026
60 days
61 days
08/30/2026
RECOMMENDED FOR APPROVAL
Project Manager
CITY OF SOUTH BEND BOARD OF PUBLIC WORKS Approved Date: __
Elizabeth A. Maradik, President
Joseph R. Molnar, Vice President
Address Murray L. Miller, Member
South Bend, IN 46619
City, State, Zip
%
%
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 09/17/2026
Name Zach Hurst Department DPW
BPW Date 09/22/2026 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 2 Traffic Control Resolution Other: Ease./Encroach
Required Information
Company or Vendor Name Ritschard Brothers
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Demolition of 747-749 Harrison Avenue
Project Number 124-062
Funding Source River West DA TIF
Account No. PO-0042853
Amount This change: $17,865; Revised Amount: $552,788
Terms of Contract
Purpose/Description Change Order no. 2 accounts for unforeseen asbestos abatement and concrete
removal.
For Change Orders Only
Amount of Increase Decrease
$ 17,865
($ ) Previous Amount $ 534,923
Current Percent of Change:
Increase
Decrease
4.0%
( %)
New Amount $ 552,788
Total Percent of Change:
Increase
Decrease
24.6%
( %)
Time Extension Amount: 61 days New Completion Date: 08/30/2026